Hi Eugene,
     They have not been forgotten, I promise. They are part of those 
upstream components that Doug mentioned.

Thanks
Denny

On 3/17/2011 3:01 PM, Eugene Pasyuk wrote:
> Tagger downstream He bag needs to be installed properly. It is detached
> and deflated now. You did not mention collimators and the shielding
> downstream of pair spectrometer.
>
> -Eugene
>
> Doug Tilles wrote, On 03/17/11 14:37:
>> To All
>>
>> The Start Counter is installed and cabled up, the alignment is on for
>> first thing in the morning 3/18/11
>> Saclay will go on the beam line right after that. Once on beam line the
>> target can be pumped on and ready for insertion and alignment.
>> The Down Stream beam pipe which is  being used as the He bag ending at
>> the alcove is in but for the last piece.
>> Monday the Pair Spec detectors will be install as well as the remaining
>> upstream components. Sweep and Harp. Than the Alignment group will do
>> the final alignment. Than the up stream He bag.   Does anyone see
>> anything I missed.  We need to be ready to run by the end of the day
>> Friday 3/25/11
>>
>> Doug
>> :-)
>>
>> _______________________________________________
>> Hallb-engineering mailing list
>> Hallb-engineering at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/hallb-engineering
> _______________________________________________
> Hallb-engineering mailing list
> Hallb-engineering at jlab.org
> https://mailman.jlab.org/mailman/listinfo/hallb-engineering





More information about the Hallb-engineering mailing list