Volker,

I have no problem with this.
We will probably have to cancel the Hall B engineering meeting, to allow 
the techs to help recover if there are problems with recovery.

Doug, George and Krister,
What do you think?

Dave


On 10/25/2011 7:02 AM, burkert wrote:
> Hi all,
>
> Does anyone have objections as to the date and time when the utility 
> power will be killed for
> the HDIce emergency power test?
>
> Volker
>
>
>
> -------- Original Message --------
> Subject: 	Hall B Power Outage
> Date: 	Mon, 24 Oct 2011 15:50:17 -0400
> From: 	Paul Powers <powersp at jlab.org>
> To: 	Doug Tilles <tilles at jlab.org>, David Kashy <kashy at jlab.org>, 
> Volker Burkert <burkert at jlab.org>
>
>
>
> To All,
>
> Power outage to confirm connection of Andy Sandorfi's equipment to
> Emergency Power Circuits.  Will kill all utility power, clean power and
> utility power in Hall B.  Only emergency power will remain on.
>
> This power outage will be done on Friday at 8:00 AM unless you get with
> me before that and arrange a different day or time.
>
> Thanks, Paul
>
>
> _______________________________________________
> Hallb-engineering mailing list
> Hallb-engineering at jlab.org
> https://mailman.jlab.org/mailman/listinfo/hallb-engineering

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20111025/7f39416a/attachment-0002.html>


More information about the Hallb-engineering mailing list