[Hallb-engineering] Update on beam status to Hall-B

Stepan Stepanyan stepanya at jlab.org
Fri Nov 7 12:13:50 EST 2014


Dear all,

 From what we had yesterday things have shifted by one shift. Machine 
will start multihall
separation work swing today. Attached is the shift schedule for Hall-B 
as we have it at the
moment. Evening shifts today are canceled. Depending on how repair work 
and HCO will
go for BSY and Halls we may or may not have night shifts, email update 
will follow late
afternoon.

Regards, Stepan
RC
-------------- next part --------------
A non-text attachment was scrubbed...
Name: comm_shifts.pdf
Type: binary/octet-stream
Size: 26358 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20141107/bb7e7a67/attachment-0002.bin>


More information about the Hallb-engineering mailing list