[Hallb-engineering] CLAS12 commissioning

Probir Ghoshal ghoshal at jlab.org
Sun Dec 17 19:09:14 EST 2017


Excellent news Volker..!
Great to be the part of the team.

Regards, 
Probir 

> On Dec 17, 2017, at 7:04 PM, burkert <burkert at jlab.org> wrote:
> 
> Dear all,
> 
> Today, December 17, 2017 at 13:13:26, the beam in Hall B was increased to 70nA. This corresponds to the design operating luminosity of CLAS12. This is a huge milestone on our way to science in 2018. All baseline detectors, superconducting magnets, and several ancillary detectors are installed and were fully operational.
> 
> While all detectors behaved as expected, some tuning of their operating parameters remains to be done for the second part of the engineering run in January.  Until then we all must do our utmost to use the large amount of data collected during this commissioning run for the calibration of all detector       components.
> 
> With the best wishes for a wonderful holiday season,
> 
> Volker Burkert
> 
>  
> 
> _______________________________________________
> Hallb-engineering mailing list
> Hallb-engineering at jlab.org
> https://mailman.jlab.org/mailman/listinfo/hallb-engineering
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20171217/99dad8c5/attachment-0002.html>


More information about the Hallb-engineering mailing list