[Hallb-engineering] Fwd: Hall B Solenoid - new delivery date (29th May 2017)

Douglas Tilles tilles at jlab.org
Thu May 11 09:35:53 EDT 2017


FYI

----- Forwarded Message -----
From: "Ruben Fair" <rfair at jlab.org>
To: "Joseph Matalevich" <josephm at jlab.org>, "David Kashy" <kashy at jlab.org>, "Doug Tilles" <tilles at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "George Biallas" <biallas at jlab.org>, "Probir Ghoshal" <ghoshal at jlab.org>, "Renuka Rajput-Ghoshal" <renuka at jlab.org>, "Denny Insley" <dinsley at jlab.org>
Cc: "John Hogan" <hogan at jlab.org>, "Glenn Young" <gyoung at jlab.org>
Sent: Thursday, May 11, 2017 9:23:00 AM
Subject: Hall B Solenoid - new delivery date (29th May 2017)

All, 

The new delivery date for the solenoid is now 29th May 2017. 

Please inform your sub-team members and their home supervisors. 

I am reworking our detailed installation and commissioning plan and will be re-issuing it shortly. 

HR and Payroll will also be providing us with some updated guidelines (following our meeting with them about a week ago) - I shall distribute these as soon as I receive them. 

Regards 

Ruben