[Hallb-engineering] Fwd: Hall A Facility Development Schedule
Stepan Stepanyan
stepanya at jlab.org
Tue Oct 23 16:22:07 EDT 2018
Dear all,
Below is the schedule for next two days from PD. As of now we expect to be down from 9 am tomorrow, Wednesday, October 24, till at least swing on Thursday. Most likely we will be down till Friday day shift. So, Hall-B's plans during these days will be:
- 9am beam off, will start turning magnets off (solenoid and torus) - magnet experts
- Hall will go to the restricted access, ~10 am - shift expert
- planed work will start in the hall ~10 am - detector experts, engineering
- we will keep hall open until plans for beam to physics finalized (most likely will stay open till Friday morning)
Please coordinate with Sergey if you need DAQ, I know CTOF and HTCC wants to do calibration runs, also there is a request to do cosmic run for the forward carriage detectors (can be done overnight). We have time to do all, just need a coordination. Please let me know if you have any questions.
Regards, Stepan
RC
> Begin forwarded message:
>
> From: Joseph Meyers <meyers at jlab.org>
> Subject: Hall A Facility Development Schedule
> Date: October 23, 2018 at 4:04:27 PM EDT
> To: Vladimir Berdnikov <berdnik at jlab.org>, Ciprian Gal <ciprian at jlab.org>, Stepan Stepanyan <stepanya at jlab.org>, ben Zihlmann <zihlmann at jlab.org>
> Cc: Steven Suhring <suhring at jlab.org>
>
> Run Coordinators,
>
> The schedule for the Hall A Facility Development run is up on the white board.
> Based on the current schedule, Friday day shift will be when physics resumes and when you should man your staff. Depending on how things go, we could start earlier. As we get through Thursday day shift, we will know more. It is an aggressive schedule but is why we included those float shifts.
>
> Wednesday, 10/24
> Day Shift:
> - Injector checks at 9AM (3 hrs.)
> - 1C12 Scans (4 hrs.)
> Swing:
> - Arc 1 & 2 Calibration (8 hrs.)
> Owl:
> - Phaser SL & NL
>
> Thursday, 10/25
> Day:
> - MOmod (8 hrs.)
> Swing:
> - Float if needed
> Owl:
> - Float if needed
>
> Friday, 10/26
> Day:
> - Physics resumed
>
>
> OPS White Board Schedule: http://accboard.acc.jlab.org/
>
> Please let me know if you have any questions about the schedule.
>
>
> Joseph Meyers
> Magnet Measurement Group
> Jefferson Lab
> (757) 269-7655
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20181023/2d44ccb5/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: JLabEmailSig.png
Type: image/png
Size: 7082 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20181023/2d44ccb5/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: whiteboard.jpg
Type: image/jpeg
Size: 181333 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20181023/2d44ccb5/attachment-0001.jpg>
More information about the Hallb-engineering
mailing list