Logentry Text:
--
Dear Collaborators,
I am very happy to report the target installation work is make good progress, gratitude to the target experts who started early and stopped very late last night.
Please see some the target alignment pics: https://logbooks.jlab.org/entry/3832240
Despite the great progress, we had a few minor issues which caused some delay. Please see a progress report in JP's log entry at 2 am (https://logbooks.jlab.org/entry/3832227). The target work will continue today. In general, based on my conservative estimation, we are still on track to leave the target polarized tonight and start production sometime tomorrow. There is no change in the shift status, if your shift is in on-call status, please stay close to your phone during the shift hours.
Also accelerator has been sending beam to other halls since 8pm last night.
There will be no 4:15pm RC meeting today.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3832367
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20200822/3798ccc5/attachment.html>
More information about the Hallc_running
mailing list