Earlier this morning around 6:30 am, Hall C dropped out of beam permit when a group of the run/safe boxes dropped https://logbooks.jlab.org/entry/4091561 SSG came on site and Radcon was notified for a sweep.

It turned out that PSS system B, Module #11 passivation caused associated run/safe boxes to drop https://logbooks.jlab.org/entry/4091590. Power cycling the module and remote I/O PLC unit resolved the issue. A full survey of the hall was done, run/safe boxes were reset. 

We're back in the beam permit and ready for beam! We will resume production data taking once beam is back in Hall C.

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4091594
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20221126/9478a43b/attachment.html>


More information about the Hallc_running mailing list