Yesterday beam was restored around 8pm after the ARC9 down. After restoration, we completed the Tin running on setting 1 of HMS-20 degrees, SHMS-8 degrees.

There was an issue in the injector around 22:45, which was resolved at 01:30 this morning. We continued on with the run plan until the planned down for the Accelerator Reliability Workshop at 07:30 this morning.

Shortly after 09:00, the hall entered restricted access for the tour groups. The technical team is currently in the hall replacing the SHMS side camera and then will work with engineering staff to replace the SHMS Q1 vacuum gauge.

The tours should conclude around 13:00, when the North Linac and Hall C will have sweeps to go back to beam permit.

As soon as beam is restored, we will continue on with our setting 1 runplan. Later this week, we will do a BCM calibration and beam energy measurement.

In my last hours as RC, I'd like to give a huge shoutout to the Technical and Engineering staff. This past week there have been many big events that required their expertise to resolve. They have worked extremely hard to help keep us up and running as much as possible. Thank you to all of them for keeping us afloat.

We'll have an RC meeting today at 11 (~10 min from now):The Zoom connection information:

Join ZoomGov Meeting
https://jlab-org.zoomgov.com/j/1607100885?pwd=ZFBsRTFsYm5Zb0laZ0tyZXNjcEE0QT09

Meeting ID: 160 710 0885
Passcode: 595071

Happy Shifting,
The Scraggly (Feral?) Postdoc

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4063207
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20221019/b3bc51bd/attachment.html>


More information about the Hallc_running mailing list