[Hallc_running] [New Logentry] Hall C RC update: Wednesday, January 11

gaskelld at jlab.org gaskelld at jlab.org
Wed Jan 11 09:15:01 EST 2023


Logentry Text:
--
Hall C was locked up and taken to beam permit yesterday on swing shift as planned.  Tune beam was sent to the hall and initial harp scans (for the harps near the target) look good.  This morning the hall was taken to Controlled Access and the target cooldown is underway.

Since the near term runplan was decided yesterday, there will be no RC meeting today.  Note however that we still need target operators tonight for swing and owl shifts - please sign up if you are able.

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4107237
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20230111/a49ea081/attachment.html>


More information about the Hallc_running mailing list