[Hallc_running] [New Logentry] Updated plan for tomorrow's access
sanghwa at jlab.org
sanghwa at jlab.org
Wed Feb 21 14:55:01 EST 2024
Logentry Text:
--
We will go to controlled access for the NPS colorimeter work tomorrow morning. We will remain open till Friday morning and switch to KinC_x36_6.
Preparation for the access and NPS work:
1. Beam off at 7:30am
2. Rotate SHMS to 38.00 deg -- Do not rotate the spectrometer if GUI and TV values don't match. Contact Ellen or Steve L in that case.
3. RadCon survey shortly after that
4. Lock-out, Tag-out NPS Sweep (Joe Beaufait) around 8:30-9:00 AM
5. Techs move the NPS detector to 6m
Work planned in the hall tomorrow:
- Remove some of NPS columns for refurbishment (RadCon support confirmed on the column survey)
- Techs remove Pb Shield from back of NPS Sweep Magnet
- Heidi have a list of small work items that don't take long time
All relevant personnel (MCC, RadCon, Jerry, Joe) have been contacted and confirmed the schedule. Please let the RC know if you have some work to be done in the hall.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4255004
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20240221/cf5db683/attachment.html>
More information about the Hallc_running
mailing list