[Halld-cal] Draft level 5 CR for Bcal and Fcal activities
Matthew Shepherd
mashephe at indiana.edu
Thu Oct 1 14:38:29 EDT 2009
Hi Elton,
A delay of 48 weeks sounds reasonable for the FCAL. This gives us
some time to make a definite decision and begin fabrication of the
system.
-Matt
On Oct 1, 2009, at 2:21 PM, Elton Smith wrote:
>
> Hi Matt and Christina,
>
> Below are the proposed schedule changes to the Fcal and Bcal
> activities to
> implemented in a change request this month. Please comment.
>
> -------------------------------------------------------------------------
> We would like to adjust the schedule for some activities (no change in
> cost), which are indicated below. I briefly spoke to Pat and he
> quickly
> checked that there would be no obvious impact on successor
> activities with
> the proposed changes. This of course should be verified with a "what
> if"
> schedule. We would like to implement the CR this month to avoid
> starting
> the Fcal monitoring activity (15222080), which is currently
> scheduled to
> start in October 2009.
>
> Activity Name Float Change
> 15221155 Winston Cones 39 delay +24
> 15221170 Signal Cables 47 delay +24
> 15221171 HV SiPM Cables 49 delay +24
> 15221172 HV PMT Cables 49 delay +24
> 15221173 Light Guides 80 delay +24
>
> Justification: Will require time to finalize adjustments to Bcal
> readout
> once final decision is made.
>
> Activity Name Float Change
> 15222080 Fcal Monitoring 83 delay +48
>
> Justification: Will require feedback from Fcal module fabrication
> contract
> to define interfaces for monitoring of the lead glass.
> ---------------------------------------------------------------------------
>
> Elton Smith
> Jefferson Lab MS 12H5
> 12000 Jefferson Ave
> Suite # 16
> Newport News, VA 23606
> elton at jlab.org
> (757) 269-7625
> (757) 269-6331 fax
>
More information about the Halld-cal
mailing list