[Halld-jlab] Notes, Hall D Staff Meeting, 9/13/10
Mark M. Ito
marki at jlab.org
Mon Sep 13 16:59:34 EDT 2010
Find the notes from the Hall D Staff meeting of Sep. 13, 2010 at
http://www.jlab.org/Hall-D/software/wiki/index.php/Private:Hall_D_Staff_Meeting%2C_September_13%2C_2010
and reproduced below.
Private:Hall D Staff Meeting, September 13, 2010
Present: George Biallas, Eugene Chudakov (chair), Hovanes Egiyan, Mark
Ito, David Lawrence, Lubomir Pentchev, Yi Qiang, Elton Smith, Sascha
Somov, Simon Taylor, Tim Whitlatch, Elliott Wolin, Beni Zihlmann
Announcements, Eugene
* Collaboration meeting
+ well organized
+ tour of BCAL factory was interesting
+ Decision on radiatoin hard insert
o shaslik abandoned
o crystals have advantages: resolution and existence
# add money for electronics
# magnetic shielding an issue
# frame complicated
o collaboration seemed to decide to go for glass
o need final decision soon to make manpower projections
o glass procurement will have to start soon to be in time
* Lehman review is coming, dry runs scheduled
* appraisal cycle starting Oct. 1
* accounts, end of fiscal year
+ DOPS all spent
+ some money in BIASOL, work should continue
+ 1.5 M$ in BIASOL in plan for FY11
+ this year 1.4 M$ spent
+ BIAGRP will be out of money, some redistribution of effort may
be requested
Solenoid, George
* over weekend re-calculated need for cladding on exterior of
solenoid
+ 1 m air gap used previously
+ with 4 m air gap, FCAL in 260 G field, not 150 G.
+ Tim: FCAL good to 180 G, TOF good to 200 G
+ 4-m-air-gap calculation done in 3D, includes voids where feet
penetrate
* plans now: working on connecting up chimney: connections for cryo
fluids in can leading to coil itself.
* setting up electrical connections that go through helium and
through insulation
* going on Tom's plan
+ pump down near Oct. 1
* Lehman review:
+ Tom not able to see advancing state so the cooling down can
start before review
+ Glenn Young given a bunch of stuff on Friday
+ dry run on Monday
Solenoid, Elliott
* electrical connections will be done tomorrow or the next day
* then do piping connections
+ maybe done by Monday
* controls
+ problem: getting Mark Wissmann's time
+ need remove test cables and put in real cables, need Mark W.'s
OK
+ no big show stoppers anticipated
Engineering, Tim
* clean room came in over budget, 294 k$, to be awarded soon
* trailer goes in in January
* telecom getting expensive
* got fermi to get leak detector[?]
SiPM Tests, Yi
* getting ready for radiation test
* confirming that current SiPM's...[?]
LASS Magnet Current, Elton
* 1250 A at SLAC is the lore (Steve St. Laurent)
* LASS NIM paper: 2.24 Tesla at 1600 A
Dmitri Romanov, Mark
* Started going over design document for calibration database.
FADC's on FDC Anodes, Lubomir
* charge would be available for disambiguation
* timing resolution being investigated
__________________________________________________________________
Recorded by --[19]Mark Ito 13 September 2010
Retrieved from
"http://www.jlab.org/Hall-D/software/wiki/index.php/Private:Hall_D_Staff_Meeting%2C_September_13%2C_2010"
More information about the Halld-jlab
mailing list