[Halld-jlab] Hall D Staff Meeting Notes, December 3, 2012

Mark M. Ito marki at jlab.org
Wed Dec 5 12:08:36 EST 2012


Find the notes at

 
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_December_3,_2012

and below.
___

Private:Hall D Staff Meeting, December 3, 2012

    Present: Eugene Chudakov (chair), Mark Ito, David Lawrence, John
    Leckey, Bert Manzlak, Lubomir Pentchev, Yi Qiang, Dmitry Romanov,
    Patrizia Rossi, Elton Smith, Sascha Somov, Simon Taylor, Ivan
    Tolstukhin, Tim Whitlatch, Elliott Wolin, Beni Zihlmann

Announcements, Eugene

      * Lehman Review review
           + Lab proposed re-baselining
                o CD 4A milestone stays on Jan. '15
                o CD 4B moved to Dec. '16
           + Halls:
                o good progress, but cost and schedule cannot be met,
                  mainly due to superconducting magnets in B and C
                o due to general cost trends, recommend an ETC, from bottom
                  to top
                o we will have to retain documentation for changes
           + B & C generated magnet recommendations
           + not happy with costs management by Procurement
           + de-scoping of new solenoid:
                o added 10 M$ to extend schedule
           + SVT project of Hall B praised for progress
      * exterior doors to CEBAF Center to remain mainly closed to entrance
      * promotions, Rolf has a condition: responsibilities must have
        changed

Safety, Bert

      * recent annoumcement about General Access Radiation Work Permit
        pertains to the 2012 version
      * training for the 2013 has not been issued yet, but will be soon

Installation, Tim

      * solenoid review
           + need to finish paper work
           + going in right direction
           + OSP forthcoming
      * solenoid systems
           + helium, nitrogen, and vacuum all lead checked
           + will start cooling Dec. 17
           + power supply turn on Fri., OSP in place
           + Jan. 9: review for powered operations
           + meeting was held today for planning for powered operations
      * tagger
           + Bill Crahen visited manufacturere, accepted the magnet
           + worked as it should, holding off on delivery
           + tagger gantry still needs load testing.
           + vacuum chamber probably here in January
           + tagger hall ODH assessment complete (verbally)
                o Hall will have to have monitoring done as well
      * extra A/C in EEL 126: installation underway

FDC Construction, Lubomir

      * techs are back!
      * package 1: finished, subsystems installed, finishing wiring for hv,
        ready to test, will move after shutdown
      * package 2: last one to finish, working on cathodes, all wire frames
        ready, all materials in hand, done by January
      * package 3: tested in EEL 126, moved to Bluecrab before
        Thanksgiving, connected to nitrogen to test, small leak found,

    over-pressured by mistake, pressure 350 Pa on input to dewar
      * package 4: finished before Thanksgiving, Vlad tested, found broken
        field wire, not clear how that happened, one week after closing it,
        prbably a kink waiting to go, replaced last week

Calorimetry, Elton

      * planning for shipping FCAL frame
           + will be ready in a week
           + John Frye will come here when time to align shims for blocks
      * BCAL
           + parts are all on order, read-out boards have been shipped,
             hoping to have 1st article soon, then all boards in Jan.
           + jumper maps ready this month to be ready for installation
                o will take a couple of months
           + waiting on light guides, 800 last week, almost a 1/3 on site
             now, another shipment today or tomorrow
           + glueing manpower need to be coordinated
                o Tina and Mike will work on it
           + have 400 LEDs on hand, rest shipped this month
      * attending GSI collaboration meeting next week
           + discussions for collaboration with GSI/PANDA
           + discussion of virtual institute
                o everyone is interested but change of management structure
                  at GSI right now
                o delay in signing agreement

Tagger, Sascha

      * microscope contract
           + dispute resolution discussion on-going
      * fixed array
           + Dan Sober close to finalizing size of counters
           + will need to regenerate field map, but current map good enough
             for design
           + PMTs: Franz Klein received two tubes
                o he will be here for two days, prepare a set-up for
                  testing
           + Vladimir Popov, of Radcon, will design amps for the PMTs
                o he did similar amplifiers for Hall C
                o amplifiers needed to reduce charge on anode
                o schedule tight, 4-5 months lead time for tubes

Pair Spectrometer, Ivan

      * working on gluing jig with Anatoly Sitnikov, hope to order fixture
        soon

CDC Construction, Beni

      * Lubmori and Beni decided on gas system:
           + FDC can handle 40-60 to 90-10 mixture with 1.5 overhead for
             maximum flow
           + for CDC have factor of two
      * want to measure continuity at CMU before closing plenum, now that
        boards are installed
      * issue with sealing neoprene between endplate and Swiss cheese
        plate: cracked, causing leak
      * Tim on gas system: Narciso Gomez spec'ing out components, has a
        spec that Tim will review, will make a gas panel, he is also
        designing an alcohol bubbler, both in one fridge
      * Lubomir tired one oil bubler design, but not with low pressure in
        chamber, can add volume in front of bubbler

Time-of-Flight, Start Counter, Mark

      * No TOF meeting in some time
      * Chuck Hutton is waiting for feedback on the support structure from
        the mini-TOF construction effort
      * Start Counter has issues with crazing from manufacturer McNeal
           + happens several weeks after counters are received
           + will make an effort to improve handling procedures
           + will research possible role of heating and bending
      * SiPMs for more boards have arrived at JLab

Around the Room

David

      * working on data acquisition event source
           + have a version with EVIO low-level objects
           + Dave Abbott made the libraries, changes needed to make it able
             to read multi-event blocks with no dis-entangling, allow
             accepting event from ET or file
      * implemented MD5 check sums to fingerprint geometry
      * wrote new tool to use command line to see where you are in geometry

Beni

      * learning CSS for FDC and CDC HV and LV applications
      * working on making material in front of TOF more realistic, add
        structures involved in holding system together

Sascha

      * Vardan working with him on template funcions for board
        initialization
      * have a process running that talks to run control
      * uses config files with parameters: write them, check with read
      * Vardan working on interface for trigger control, pre-scale factors
      * with Dmitry: write these parameters to db

Ivan

      * AC for EEL 126 looks good, no water drops on gluing system
      * when that is done will test cross talk and after-pulsing

Dmitry

      * continuing with trigger, adding gui
      * group decision to switch to CCDB on Jan. 1
      * tried to load geometry to EVE, geometry browser, worked well
           + projections next
           + also need to incorportate into JANA

Elliott

      * protoype monitoring farm work
           + one node working, other three done today
           + preliminary tests, injected events into ET system at 500 kHz
      * getting elog installation a week from today
      * EVIO improvements coming in
      * re-ordering events will not be done
      * controls for solenoid under control
      * counting house furniture being planned

Hovanes

      * finished adding command line options for scripts for PLC interface
        to EPICS
      * working on EPICS support for FADC modules, to be able to read
        parameters of FADC-250 and read scalers
      * counting house: starting to procure equipment, will need everything
        finished by Jan. for racks to be complete, then computers and file
        servers can be installed

Simon

      * working on geometry in simulation
           + changes to CDC geometry
           + BCAL issues as well
      * working on tools for vertexing for use by Paul

Mark

      * working on data challenge

Yi

      * working on PLC and PXI interface system for solenoid
           + for data analysis will have root based tools
           + turn-to-turn short patterns are visible by eye now
                o working on automating recognition

John

      * working on proceedings for recent conferences
      * NIM paper on FCAL beam tests in progress

    Retrieved from
 
"https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_December_3,_2012"


-- 
Mark M. Ito
Jefferson Lab
marki at jlab.org