Present: Eugene Chudakov (chair), Hovanes Egiyan, Nerses Gevorgyan,
Mark Ito, David Lawrence, Lubomir Pentchev, Yi Qiang, Elton Smith,
Sascha Somov, Simon Taylor, Tim Whitlatch, Elliott Wolin, Glenn Young
Announcements: Eugene
* 50 M$ for FY12 for 12 GeV, much less than original plan
+ plans depend on how we shift spending from FY12 to FY13 or
FY14
* March 9: NSAC meeting to discuss future program
+ Tim Hallman has said not all NSAC recommendations can be
executed
* Physics Division budget: can we support four halls?
+ some part of personnel will be shared
+ one hall may go to sleep for years
* plans for Hall D still as they are on paper
+ beam: Spring of '14
o may be delayed to Fall
o see particles in the Hall
+ Fall of '14: Halls C and B
+ Fall of '13: Hall A
+ end of '15: Engineering Run
Baby BCAL Test: Elton
* Proposals for tests presented this morning, in Hall B meeting:
+ SOLID: Zhiwen Zhao
+ Baby BCAL (BBCAL): Elton and John Leckey
* told to work with Doug Tilles and Eugene Pasyuk on plans
* Sit in a position to get 25-30% of electron energy
+ real estate currently occupied by INFN team
* detector ready by mid-March
* FCAL prototype is up in alcove at 5% of the beam energy
* Hall B schedule:
+ this week open: change from photon to electron beam
o will look at polarization in electron beam
+ in two weeks, go back to photon running
o new target not ready yet so will take empty target data
+ mid-march new target ready
o window for installation of BBCAL
* want 5-pass beam for BBCAL
* FCAL will stay in alcove, continue with 2-pass, then look at 3-pass
and 5-pass
* SOLID wants to be downstream, 50-70% of beam energy
* design of modification of frame for BBCAL underway
+ need to turn by 90 degrees
* may need another chiller
* light guides were supposed to be shipped today
* boards look in good shape, one part will be soldered on after they
are stuffed by company
* test will have full configuration on both ends
* BBCAL length = 58 cm
Engineering: Tim
* target refrigerator arrived today, will be given to Chris Keith
* next target review: Feb. 23
* FCAL platform: hoping to get out soon for fab, need final
facilities OK
* cryo playform: final drawings being worked on
* collimator hardware coming in
* making nitrogen shield: a cryo group design, Hall D fabrication
* electrical interfaces between cryo box and solenoid almost complete
* all coils leak checked and OK
* cladding for solenoid due in first week of April
* working on baffle supports
* tools for BCAL assembly due middle of March
* vacuum chamber for the pair spectrometer, in final check, PR will
be written in next couple of days
* pole tips due in end of March
* tooling for FDC and CDC installation: design underway, should be
done by end of month
* waiting on ultrasonic test report on tagger magnet
+ then ship for final machining
+ supposed to start winding coil mid-Feb.
+ they claim that they are on schedule
* vacuum chamber for tagger: have gone on to 2nd bidder, 1st left
some stuff out, hope to be out for procurement later this week
SiPM Testing: Yi
* solved DC offset, changed from DC to AC coupling
* control software ready
* analysis software almost done
* OSP: draft written by Carl, sent to Bert, can start work upon
approval
* sensors for Baby BCAL: may be limited by PS supply voltage channels
FDC Construction: Lubomir
* the first package is in EEL 126: go there and you will see a whole
lot of cables
+ 4 cells connected to electronics, with another TDC will be
able to connect more
+ some issues with gas, leakage from area near the top spacer
ring
+ package will have to go back to Blue Crab, opened and fixed
+ package operates, stable, 1 or 2 channel tripping once a day
or so
+ Beni is analyzing efficiency, not 100% over whole chamber,
good at gas input, worse on far side
+ trying to improve the grounding
+ started with threshold at 20 V, have gone to 12 V threshold,
equivalent to 24 mV on output of pre-amps
+ grounding now not the same as it will be in Hall, Fernando
will work on it
+ efficiency does not depend on threshold, this points to gas as
the problem
* at Blue Crab production going well
+ fooling with parameters for electroplating, trying different
samples
+ 3 wire frames ready and waiting for electroplating
+ 40% of cathodes for 3rd package are ready
+ 1 wire frame had traces de-laminated at HV caps, sent to be
fixed, traces re-attached by soldering to capacitor connection
FCAL Prototype Testing Electronics: Sascha
* working with crate to set up integrate data acquisition with Hall B
crates
* need interface with old TI board, the one being used in Hall B
* one TI for read-out (old-style), one for triggering (new-style)
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_February_13,_2012"
--
Mark M. Ito
Jefferson Lab (www.jlab.org)
(757)269-5295
More information about the Halld-jlab
mailing list