Private:Hall D Staff Meeting, July 16, 2012
Present: Vladimir Berdnikov, Eugene Chudakov (chair), Hovanes Egiyan,
Mark Ito, Vanik Kakoyan, David Lawrence, Lubomir Pentchev, Yi Qiang,
Simon Taylor, Elton Smith, Sascha Somov, Tim Whitlatch, Elliott Wolin,
Beni Zihlmann
Announcements, Eugene
* operations budget: if we need it, we need to order soon
+ 20 k$ for central calorimeter
+ Panda developed APD sensor, radiation hard
+ money for future Cerenkov
+ online money exists, not as much paid to visitors as
anticipated
+ Mark: TOF amplifiers a possibility
Engineering, Tim
* tagger:
+ magnet steel OK
+ winding slipped a bit
+ vacuum chamber in Oct.
* downstream platform, most pieces in
* cryo platform due end of August
* solenoid test planning underway
+ cold in January
+ cryo tank available by end of August
* electricity for panels mostly figured out, one dirty power panel
needs to be worked out
* electrical for solenoid being installed
* grounding for hall: bonding of metal parts starting
* electrical for tagger being planned/reviewed
* LCW in tagger hall: all components in, need to start welding
* power preparations for counting house:
+ about to put in receptacles in rack room
+ start moving racks soon[?]
* power supply for tagger: we have it
+ taken out of service from accelerator
+ spare being sent to vendor for re-work
* power supply for solenoid: almost ready to move into position,
waiting for fire pipe
* frames for BCAL installation being fabricated, due end of August,
rails to be put on platform on order now
FDC, Lubomir
* looking for two wire frames to finish 4th package, selecting from
candidates
+ two draw high current
o figured out problem: removed limiting resistors on sense
wires, problem on HV board itself, traces on back side of
board touching Rohacell, explains temperature, humidity
dependence of current draw
o no trips on these boards
+ ordered more G10 to build more wire planes
* 3rd package: got clips for grounding, 1st article only, waiting for
the rest
* working on labeling of pre-amps
* 1st package waiting for dis-assembly
+ 4th packages uses mounting fixture, need to finish it before
working on 1st
* after clips received, 3rd can be moved to EEL
+ decide to clean clips ourselves
* Eugene: when will blue crab be no longer needed: L: need to keep it
for fixing area
* want to order spacer rings for cluster counting helium chamber, 2
or 4 to prove the principle, 1 ring: 2 k$
Chamber Testing, Beni
* pretty close to getting read-out system for Linux ROCs working, one
crate works, two do not yet
* using old TI[?]
* working on gas system planning, question on the number of gases to
support
Calorimeters, Elton
* FCAL
+ platform will be here soon
+ IU sending students, to be here most of next year
+ C-W bases are now coming in at an OK rate, as fast as they can
be assembled
+ all PMTs tested
* BCAL
+ light guides main critical item
o promised by end month, 1st set
o waiting for part in milling machine, under warranty, lost
or wrong part
o machining should go fast
o three stations for polishing, should keep up with
machining
+ Tom and crew constructed a vent hood to keep end of light
guides clean while gluing underway
o should be ready when light guides arrive
+ students working on monitoring system
o took data over weekend
o stability better than 1% over the weekend
+ bias to LED is lower than what was expected, 4.5 to 6 V,
+ cross talk of order 1%
+ if light guides come in by end of month, start immediately,
glue them to BCAL
+ Eugene: can monitoring system be attached after light guides
are glued?
+ when to submit PR for machining of mechanical parts, within
next couple of weeks
Electronics, Eugene
* Fernando Barbosa preparing TDC procurement
* also will likely buy CAEN TDCs for TOF
Trigger, Sascha
* got 2 pre-production boards for TI[?]
* preparing DAQ set-up for Richard Jones
+ booting ROCs from flash, 4 GB, put all of CODA on it
+ need to mount external drive for the data
Controls, Hovanes
* PRs for small items submitted: portable NIM, serial comm supplies
* ordered portable VME crate
* Vanik working on application for motors, collimator
* had meeting with Elliott, Elton, Josh Ballard: Josh has sent PR for
parts for temperature monitoring for BCAL
* counting house: Mark Stevens, Mark[?], and Tom working on
purchasing parts for power distribution in rack room
* sent first draft of MOU with Yerevan to Glenn, needed to invite
visitors, new DOE rule
Solenoid, Elliott
* need input from Tom on some mechanical tasks to be added to
schedule
* formulating goals for a test plan
+ in the goals, 1500 A, maintenance at liquid nitrogen
temperatures
* will bring in tanks when going to helium temp. to speed up cool
down
+ in future, upgrades may or may not obviate need for tanks
* OSP: try to get that before October, there may be a review from
Physics
* Accelerator e-log prototype almost ready for demo
* FPGA programming tutorial will be held
* control racks close to finished for solenoid, in the ESB
Beamline, Sascha
* preparing active collimator: tungsten blocks to be procured,
communicating with Paul Eugenio
+ quotes from 3 companies from Richard
o one too low
+ wire EDM machining[?], part of quote
* contract RFP at UConn, waiting for proposal from them
* submitted PR for procurement of SiPMs for microscope, pair
spectrometer, start counter
* Dan Sober has studied fix array counter size
* ongoing discussion on position for fixed array
+ put on focal plane
+ decide on location, fix size
+ need to study PMT choice
* this week outline contract with CUA
* pair spectrometer: need to revise tile sizes, layout of sensors,
will get help from Fernando
+ need to finalize plate size, then order
* Ivan Tolstukhin coming August 1st: will work on SiPM testing,
timing measurements
* Arizona State very active
+ with Mike Dugger, discussed layout of vacuum box, placement of
triplet polarimeter, harp location
+ they have preliminary design, given to Slava Razmyslovich
+ need a MOU with ASU, probably a collaboration MOU, should be
related to 12 GeV
+ Ken Livingston was at meeting last time. They will install
polarimeter detector at Mainz
Goniometer, Eugene
* goniometer specs received from Ken
* question: fast shutdown signal when target not hit in the right
place required in Hall A, preference for a hardware system,
* Hall D: how to do this with so many degrees of freedom?
+ will mount several crystals on radiator wheel
+ need amorphous radiators as well
o may need another ladder for these
Pair Spectrometer, Sasha
* ordered PMTs for low granularity hodoscope
* contacted company for dividers
Offline, Mark, David
* data challenge meetings have started, bi-weekly
* ongoing work on tracking, calorimetery
* Geant4 Tutorial held last week
* Elton: what about extraneous showers in calorimeters?
+ David: some BCAL work has been paused pending new hit output
form
+ Mark: Will Levine has been making progress, but still more to
do
+ Mark: we could probably use a bi-weekly, automatic,
single-photon reconstruction job