[Halld-jlab] Hall D networking needs during the long down

Hovanes Egiyan hovanes.egiyan at gmail.com
Fri May 18 14:53:30 EDT 2012


We probably need networking in the Blue Crab facility.

On 05/18/2012 02:48 PM, Elliott Wolin wrote:
> Hi,
>
> Below is the note I intend to send to Andy.  Please check I've got
> everything correct and I haven't forgotten anything.  Send me comments
> as appropriate.
>
> Thanks,
>
>
> ==============================================================
>
>
> Dear Andy,
>
> Networking needs for Hall D during the long down are described below.
>
> In general, outside the Hall D complex existing lab networks should
> suffice, and short, planned outages are not a problem.  We will
> construct the Hall D complex network as needs arise and as other work
> permits.  Somewhat late in the down period we will perform high-speed
> testing of the hall complex network system and the connection to the
> tape silo.  Note that the direct connection between Hall D and the
> Tagger Hall will be made using JLab (dark) backbone fibers.
>
> We require networking in the following locations outside the Hall D
> complex, and normal JLab networks should meet our bandwidth requirements:
>
> CC F117:  Electronics construction and testing.
>
> EEL 126:  Detector construction and testing.
>
> ESB:  Detector construction and testing.
>
> CC F-Wing Offices:  Occasional electronics programming and testing.
>
>
> Let me know if you need additional information.
>
>



More information about the Halld-jlab mailing list