[Halld-jlab] Hall D Staff Meeting Notes, September 8, 2014

Mark M. Ito marki at jlab.org
Wed Sep 10 14:53:57 EDT 2014


Folks,

Find the notes below and at

https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_September_8,_2014

   -- Mark
___________________________________________

Present: Fernando Barbosa, Vladimir Berdnikov, Eugene Chudakov (chair), 
Mark Dalton, Alexandre Deur, Hovanes Egiyan, Sergey Furletov, Nerses 
Gevorgyan, Mark Ito, Vanik Kakoyan, David Lawrence, Lubomir Pentchev, 
Serguei Pozdniakov, Yi Qiang, Patrizia Rossi, Elton Smith, Sascha Somov, 
Simon Taylor, Tim Whitlatch

=Long Range Plan, Patrizia=

* nuclear structure and astrophysics had town meeting in August
** recommended operation of existing facilities, JLab12, FRIB
* our town meeting this weekend at Temple
* fundamental symmetries will be in Chicago
* first LRP meeting in November

=Schedule, Eugene=

* may start to tagger hall as early as 9/22
** hall will have to be closed
* 9/29-10/3 official photon beam tuning time
** have to build one shielding wall in tagger hall; no time to make 
labyrinth and take it out for installation of tagger components

=Project, Eugene=

* 2 weeks to end of project
* 600 k$ in obligated and pending
** about 100 k$ in F125s
** radiation monitors for tagger hall 20 k$
** Hall probe for pair spectrometer magnet, due to solenoid, 10 k$
* will need change request for some items

=Work in Hall, Eugene=

If you have any work that needs to be done in the Hall contact Tom 
Carstens, the work coordinator so he can identify conflicts and 
coordinate work.

=More on Schedule, Eugene=

* 10/4-10/7: take data
* after that take break, install tagger equipment, 10/7-10/14 
accelerator commissions separator
* take data as much as possible after that during October
* after that: we might get beam nights and weekends through Nov.
* Hall D has priority until end of Oct.
* in December, Halls A and B may want beam

=Checklists, Elton=

* must be done before we run
* some systems still need checklists
* some systems need update, details

=Safety Training, Elton=

* Many took SAF113 last week
* another session Tue.
* perhaps another on Thu

=Other Run-Related Items, Elton=

* subsystem on-call cell phones are here
* phone numbers are on ops wiki
* pictures related to safety systems in Hall are available

=Shift Scheduling, All=

* Much discussion
* Mark will draft a schedule on Tuesday

-- 
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295



More information about the Halld-jlab mailing list