Hall D Staff Meeting, October 30, 2017
From Gluex PRIVATE Wiki
Present: Alex Austregesilo, Thomas Britton, Eugene Chudakov (chair),
Mark Dalton, Hovanes Egiyan, Sergey Furletov, Mark Ito, David Lawrence,
Paul Mattione, Lubomir Pentchev, Patrizia Rossi, Elton Smith, Sascha
Somov, Tim Whitlatch
Contents
* 1 Announcements
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_October_30,_2017&printable=yes#Announcements>
* 2 Run Preparations
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_October_30,_2017&printable=yes#Run_Preparations>
* 3 Data Analysis
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_October_30,_2017&printable=yes#Data_Analysis>
* 4 Visitor
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_October_30,_2017&printable=yes#Visitor>
* 5 DNP
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_October_30,_2017&printable=yes#DNP>
Announcements
* Eugene and Patrizia: no change in accelerator schedule.
* Eugene: solenoid at 1345 A
o Fri. magnet tripped at 140 A.
o coil 2 had voltage spike, opposite in sign from direction of ramp
o spikes seen before had same sign
o during dump, large spike seen, 10 V for milliseconds
* Eugene: box for DIRC transport left IU today bound for SLAC
o bar box will be picked up and driven to JLab
Run Preparations
* Mark: target and start counter inserted into bore
o discriminator scalars working for all channels
* Tim: Items from the Hall
o muon detector frame pieces cut
o DIRC work suspended due to magnet testing
+ lifting fixture design on to analysis and then review
o HCO starting for all systems
o Rapid access hardware and cabling in place
+ system could come live next week
* Sascha: problem in TDC crate for tagger, muon crate not powered yet
* Lubomir: LV module for FDC having problem
* Hovanes: negative HV channel disrupting EPICS with nonsense
messages, could be entire crate
* David: raid disk chassis arrived without second pot to connect to 2
servers (for backup)
o New chassis has arrived, Paul Letta swapping to it now
* Sergey: of the 4 nodes used as Data Concentrators, only two are
fully functional.
o we may purchase a backup or two
Data Analysis
* Alex: analysis launch in progress, going slowly, on 2017
low-intensity data
* Elton: problem in BCAL matching to charged tracks
o only known change: new material map for BCAL in CCDB
o Simon has studied this, does not see an effect
* Paul: plan to start reconstruction of all Spring 2017 data by Fri.
o need final check on FCAL calibrations
o need to deal with BCAL matching issue
Visitor
Eugene: Wed. we will get a visit from the nominee for under secretary
for science
DNP
David: mini-symposium went well, many well-presented talks, significant
audience
Retrieved from
"https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_October_30,_2017&oldid=3200"
* This page was last modified on 30 October 2017, at 17:19.
* This page has been accessed once.
--
Mark Ito, marki at jlab.org, (757)269-5295
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-jlab/attachments/20171030/40acf2a1/attachment.html>
More information about the Halld-jlab
mailing list