    Hall D Staff Meeting, October 15, 2018

 From Gluex PRIVATE Wiki

Present: Alexander Austregesilo, Fernando Barbosa, Thomas Britton, 
Eugene Chudakov (chair), Mark Dalton, Alexandre Deur, Hovanes Egiyan, 
Sergey Furletov, Mark Ito, Lubomir Pentchev, Patrizia Rossi, Elton 
Smith, Sascha Somov, Tim Whitlatch, Beni Zihlmann

  * Announcements (Eugene)
      o Joe Scarcello has retired from the Lab. The new CFO is Jennifer
        Logan.
      o Budget for NP for FY19 up 6 M$ to 690 M$. Portion to Lab not
        known yet.
          + There will be a budget review here Oct. 19
      o University contracts will require more documentation
      o You have to apply for foreign travel approval even if the cost
        of the trip is being paid by others.
      o Appraisal process has started
          + Above average scores on core expectations on self-evaluation
            will require detailed written explanation
      o Registration for ORCID
        <https://blog.inspirehep.net/2015/04/what-is-orcid-and-how-can-it-help-you/>
        is encouraged
      o Summer running
          + Hall A will run, for PREX
          + Hall B will want to run HPS at 5 passes
          + Hall D can run at 5.5 GeV
          + Hall C may run for a short period, not at same time as Hall D
          + Hall D running
              # Need 2 weeks to make it worth it
              # Measure known cross section at low energy, calibration
                exercise
              # Collaboration will have to discuss plans
  * CompCal installation
      o Tim:
          + dark box will be closed by weekend
          + bring detector to Hall next week
          + if break in running now
              # hookup other ladder
              # start on water panel
          + PVC beam pipe: parts all in, thin windows[?]
      o Sascha:
          + detector will be ready this week
          + in Hall: first test plumbing
      o Beni:
          + 1.5 day break in schedule (missing now?) could be used for
            installation
  * Run schedule, Elton
      o run until 11/26, then switch to CompCal commissioning?
      o Eugene:
          + want 3 weeks of CompCal commissioning before break
          + 3 day down after high energy running over
          + no DIRC
          + answer question: is PrimEx ready to run?
          + central FCAL not calibrated but needed for Compton acceptance
          + idea: install during day, run at night during high-energy
            period
              # buys more testing time at low energy
          + collaboration agreed schedule: CompCal installation 19 Nov.
            to 3 Dec.

Retrieved from 
"https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_October_15,_2018&oldid=6156" 


  * This page was last modified on 15 October 2018, at 19:01.
  * This page has been accessed once.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-jlab/attachments/20181015/6b58cac5/attachment.html>


More information about the Halld-jlab mailing list