[Halld-jlab] Hall D Staff Meeting Notes, September 17, 2018

Mark Ito marki at jlab.org
Mon Sep 17 16:40:37 EDT 2018


Folks,

Please find the notes below and at this link 
<https://halldweb.jlab.org/wiki-private/index.php/Hall_D_Staff_Meeting,_September_17,_2018>.

   -- Mark

_______________


  Hall D Staff Meeting, September 17, 2018

 From Gluex PRIVATE Wiki

Present: Alexander Austregesilo, Eugene Chudakov (chair), Hovanes 
Egiyan, Sergey Furletov, Mark Ito, Elton Smith, Tim Whitlatch, Beni 
Zihlmann

  * Announcements (Eugene)
      o the Lab will soon convert to total time accounting
      o IT is getting rid of Zimbra. Replacement unknown at present.
      o Job description components will change
      o July: CD0 for another wing of CEBAF Center approved. Wing D
      o EIC: JLab will finish pre-CDR by end of month
      o Software and Computing Review (Director's Review)
          + all Halls, Computer Center, requests for resources,
            provision of resources
          + Hall B, Super Big Bite, Moller and Solid special attention
          + Nov. 27, 28
      o Running plan proposed: keep schedule as is, move lost time to
        end of March
          + How experimental time accounting will apply not clear
          + Issues: low/high energy running periods, installation
            activities, commissioning installed detectors, low-energy
            physics,...
      o Spin conference: considerable interest in J/ψ result
          + connection between proton mass and shape of J/ψ cross
            section at threshold as a function of energy
  * Sergey took some cosmic data
      o with new CODA
      o also did test of C-based event builder using simplified EVIO format
  * Elton on detector turn-on problems
     1. tagger HV channel won't come on
     2. FDC chiller: interlock needs to be defeated before attempting
        turn on, Lubomir got it going
     3. Upstream BCAL chiller looks good now
  * Hovanes: no spare chiller
  * Eugene: PAC and lab management interested in seeing a white paper
    from Hall D
      o nuclear targets
      o polarized target
      o K_L
  * Tim on Hall preparations
      o BCAL chiller back
      o solenoid liquid level measurements: no joy
      o spare chiller would cost $13k
      o DIRC optical box in ESB
          + mirror box due Wed.
      o CompCal moving along, restack decision to come
  * Elton: quarterly DOE report on scientific output of Lab
      o for staff: put things in publication database, info can be
        pulled from there
      o gave Linda point to GlueX list of talks

Retrieved from 
"https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_September_17,_2018&oldid=6038" 


  * This page was last modified on 17 September 2018, at 16:38.
  * This page has been accessed once.

-- 
Mark Ito, marki at jlab.org, (757)269-5295

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-jlab/attachments/20180917/6a0bd856/attachment.html>


More information about the Halld-jlab mailing list