Hall D Staff Meeting, January 25, 2021
Present: Alexander Austregesilo, Eugene Chudakov (chair), Mark Dalton,
Alexandre Deur, Hovanes Egiyan, Sergey Furletov, Mark Ito, Igal Jaegle,
Keigo Mizutani, Patrizia Rossi, Sascha Somov, Simon Taylor, Tim
Whitlatch, Beni Zihlmann
Contents
* 1 Announcements, Eugene
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_January_25,_2021&printable=yes#Announcements.2C_Eugene>
* 2 Work in the Hall, Tim
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_January_25,_2021&printable=yes#Work_in_the_Hall.2C_Tim>
* 3 Crystals, etc., Sascha
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_January_25,_2021&printable=yes#Crystals.2C_etc..2C_Sascha>
* 4 FCAL Base Repairs, Mark D.
<https://halldweb.jlab.org/wiki-private/index.php?title=Hall_D_Staff_Meeting,_January_25,_2021&printable=yes#FCAL_Base_Repairs.2C_Mark_D.>
Announcements, Eugene
* Rolf Ent stepping down as AD
* New run schedule about to be announced:
o start Aug. 23, '21, run until Dec. 20
o next run starts Feb. 23 '22, run for 14 weeks
o schedule has implications for CPP installation
+ period after '21 run too short for complete install
* Matt Shepherd has asked about how we will run shifts
o Will likely go back to the one-person, six-hour shifts
o Hovanes: need method for training new collaborators to take
one-person shifts if that becomes the norm
o Mark I: collaboration board needs ideas on how to compensate
local collaborators for taking all of the shifts
Work in the Hall, Tim
* main item: mirrors, get 'em going
o tests ongoing
o need to take down North box
o make a decision for the long-term plan
* chillers:
o need checks
o one this week, one next week
* Scot working on cooling system for magnet power supplies
* 3-D printing continues...
* CPP
o total: 3 month installation
o tasks to move before '21 run
+ dark room modifications
+ pre-position detectors
+ need to think about adding to this list
o procurements
+ all stand drawings about to be released
+ PR coming this week, 23-29 k$
+ 3-4 months for fabrication
Crystals, etc., Sascha
* Crystals
o two batches received, 350 crystals
o another batch to arrive soon
o testing at TEDF
+ visual inspection
+ measure dimensions
+ light transmission measurements
# compare with pre-selection data from Jane (no surprises
thus far)
o fabrication modules started
o a few done
o procedure will be modified (brazing temperature adjustment)
* CompCal
o improvements to LMS
o larger optical fibers
o increase LED light intensity
o tests of modified bases
+ linearity of amplifier
+ using set-up in lab
+ Fernando will order board when design finalized
* tagger hodoscope
o a few need repair
o will do the work this summer
FCAL Base Repairs, Mark D.
* Chris Stanislav and/or Nick Sandoval will remove another 100 bases
* all 200 will be re-installed when repairs are done.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-jlab/attachments/20210125/c43882c1/attachment.html>
More information about the Halld-jlab
mailing list