Hall D Staff Meeting, April 5, 2022
Announcements, Eugene
* Accelerator SAD work on track
o beam in Hall starting in June
o mid-April: CHL1 will go to 2K
* HUGS will be in-person this year
* New Lab Occupational Medicine physician on-board
* New head of Tech Transfer for Lab on-board
* Rusty Sprouse, head of Facilities, will retire in November
* Run Around scheduled for May 25
* Budget
o still on CR spending basis, no big procurements allowed
o FY22 looks good, President's FY23 has smaller increase
* Accelerator power limits are under discussion
o Main effect is on current limits for Halls A and C
o proposal: increase to 1.1 MW from 0.9 MW
o limit is administrative, not imposed by physical infrastructure
o going to 2.0 MW attractive, but would require modification to
the dumps
* New Hall D positions
o applications in for two positions
o 5-6 candidates will be invited for interviews
o Boris Grube has obtained his visa
* Alex: status of requirements for on-site work?
o Eugene: on-site work is allowed, but not required
o expect announcement from Director's Office on new policy soon
Work in Hall, Tim
* we start Hot Check-Out in six weeks
* finishing CPP installation
o still need signal cables
o will use 3×3 Crystal array for TAC
o need helium bag inside CDC
o target pieces fiducialized, install them near the end
* chiller maintenance: replace some bad pressure gauges
* beamline vacuum pump maintenance to be done
* FCAL2 drawings getting finalized
* K_L : target temperature calculations underway
* dates for Hall PSS system checks not set yet
CPP/NPP Preparations, Beni
* MWPCs have been installed
o first 3 chambers have been checked, some low-level noise to be
addressed
o missing most of the signal cables, first batch was due in last
Friday, will check with Chris Stanislav on that
* scintillator paddles are installed, but not cabled up
* muon trigger using paddles not set-up yet
* F125 CDC crate re-located for use with MWPCs
o ethernet connected
o still need fiber to connect TI to TS
* additional CAEN TDC installed for scintillator channels
o Sergey performed the needed firmware upgrade
o Beni will adjust the least-count resisters, do the integrated
non-linearity correction calibration
FCAL2 Preparations, Eugene
* modules are being produced a rate of about 30 per week
* labor-intensive activity, students from various institutions have
and will be involved
JT2GO Demo
Tim invited us: Friday, April 8 1:00 pm on Teams (see your calendar entry).
Our Hall D Engineering co-op student (Anthony Palazzo) will be giving a
demonstration of how to use free software to pull up 3D models of Hall D
equipment and easily manipulate and measure things. Anthony and
Stephanie have been working over the past few months to put this together.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-jlab/attachments/20220405/7eeb3feb/attachment.html>
More information about the Halld-jlab
mailing list