[Halld-pid] Start Counter Meeting Minutes, April 17, 2014
Mark Ito
marki at jlab.org
Fri Apr 18 11:42:03 EDT 2014
Folks,
Please find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_April_17,_2014#Minutes
-- Mark
___________________________________________________________________
GlueX Start Counter Meeting, April 17, 2014
Minutes
Present:
* FIU: Werner Boeglin, Eric Pooser
* JLab: Fernando Barbosa, Eugene Chudakov, Mark Ito (chair)
Electronics
Fernando gave us a report.
All fabrication of ST-1, ST-2, and ST-3 boards is done. The signal
split for ADC and TDC is now done on ST-3, not on ST-2 as before. The
ST-3 testing is complete. The pre-testing (checking SiPM connections,
etc.) of the ST-1s is done and the 10 ST-2s are being tested now. That
should be done by tomorrow. After that the 30 channels on the ST-1s
will be tested with a laser in the dark box. Also a test will be done
to measure the electronic component of time resolution using the laser.
It has a 100 ps rise-time and negligible jitter. This will be done with
a complete chain from ST-1 to ST-2 to ST-3 to discriminator to TDC. A
diffuser is used so that all four SiPMs can be illuminated. A set of a
few amplitudes will be measured, and both ADC-bound and TDC-bound
signals will be looked at. All tests should be done by the end of the
month.
On the mechanical side, there is a plan to do a test fit of the
electronics on the aluminum support ring once that becomes available.
When the items have been shipped to FIU, Nick Sandoval will go down and
help to get the test set-up started. Fernando needs about one month
notice to arrange travel.
We had a discussion on the scheme for making sure that the ST-1 boards
do not short against the aluminum support ring. [Added in press: this
discussion assumed that there is no allowance for spacing washers in
the design. This turned out not to be the case; a 40 mil washer is
called out in the drawings. This rendered the discussion moot.]
The group reminded Mark that we will not ship ADCs, TDCs, or
discriminators to FIU for testing the detector there. FIU will use
their existing read-out electronics. We will send an MPOD and all
cables that connect the ST-2s to the ST-3. We discussed how many signal
cables need to be shipped (those running from the ST-3). We decided to
defer a decision on that.
We decided that we should do a test mechanical assembly at JLab before
shipping the support structure to FIU, including as much as is
practical: support ring to target support, ST-3 on installation cart,
cables from ST-2 to ST-3, etc. The exact plan needs to be worked out.
Schedule
Werner laid out a very rough schedule given what we know now.
1. scintillators arrive at FIU: mid-May
2. scintillator testing and detector assembly done: end of June
3. Nick visit: early July
4. testing done: end of July
5. ship to JLab: mid-August
Assembly Jig
Eric presented the final design for the assembly jig. See his slides
([18]PDF, [19]Powerpoint) for details. Eric plans to call Chuck Hutton
and discuss the design as well.
Progress at McNeal
[Added in press: Eric talked to Robert McNeal just after the meeting
and sent in this report.]
All 50 paddles have been inspected and have passed the initial QA
check. Machining of the paddles has not yet commenced. They are waiting
for the machines to finish other jobs. However, production should begin
within a week.
Robert quoted that the paddles will be shipped out to FIU, no later
than 05/02/2014 which is right at the 4 week lead time we were quoted.
Eric provided Robert with the most up to date mechanical drawing of the
paddles. There were no substantial differences between the two drawings
and this update will have no negative consequences.
Robert mentioned that they do quantify the final dimensions of the
paddles after they are machined. This is done both optically and by
machine. Standard operating procedure dictates that they will only
measure approximately 8 of the 50 paddles. He is willing to provide us
with this data. It is possible for them to inspect all 50 paddles and
provide us with their associated measurements for a minor inspection
fee initially estimated at $200.00. Further discussions will be made
regarding whether we should purchase this inspection data.
References
18. https://halldweb1.jlab.org/talks/2014-2Q/Finalized_Assembly_Jig.pdf
19. https://halldweb1.jlab.org/talks/2014-2Q/Finalized_Assembly_Jig.pptx
--
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295
More information about the Halld-pid
mailing list