[Halld-pid] Start Counter Meeting Minutes, April 17, 2014
Fernando J Barbosa
barbosa at jlab.org
Fri Apr 18 11:48:24 EDT 2014
Hi Mark,
Maybe I missed something but the spacers were always part of the design.
The question, as I understood at the meeting, was whether the spacers
provided enough precision and uniformity during attachment of the ST1s.
Best regards,
Fernando
On 4/18/2014 11:42 AM, Mark Ito wrote:
> Folks,
>
> Please find the minutes below and at
>
> https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_April_17,_2014#Minutes
>
> -- Mark
> ___________________________________________________________________
>
> GlueX Start Counter Meeting, April 17, 2014
> Minutes
>
> Present:
> * FIU: Werner Boeglin, Eric Pooser
> * JLab: Fernando Barbosa, Eugene Chudakov, Mark Ito (chair)
>
> Electronics
>
> Fernando gave us a report.
>
> All fabrication of ST-1, ST-2, and ST-3 boards is done. The signal
> split for ADC and TDC is now done on ST-3, not on ST-2 as before. The
> ST-3 testing is complete. The pre-testing (checking SiPM connections,
> etc.) of the ST-1s is done and the 10 ST-2s are being tested now. That
> should be done by tomorrow. After that the 30 channels on the ST-1s
> will be tested with a laser in the dark box. Also a test will be done
> to measure the electronic component of time resolution using the laser.
> It has a 100 ps rise-time and negligible jitter. This will be done with
> a complete chain from ST-1 to ST-2 to ST-3 to discriminator to TDC. A
> diffuser is used so that all four SiPMs can be illuminated. A set of a
> few amplitudes will be measured, and both ADC-bound and TDC-bound
> signals will be looked at. All tests should be done by the end of the
> month.
>
> On the mechanical side, there is a plan to do a test fit of the
> electronics on the aluminum support ring once that becomes available.
>
> When the items have been shipped to FIU, Nick Sandoval will go down and
> help to get the test set-up started. Fernando needs about one month
> notice to arrange travel.
>
> We had a discussion on the scheme for making sure that the ST-1 boards
> do not short against the aluminum support ring. [Added in press: this
> discussion assumed that there is no allowance for spacing washers in
> the design. This turned out not to be the case; a 40 mil washer is
> called out in the drawings. This rendered the discussion moot.]
>
> The group reminded Mark that we will not ship ADCs, TDCs, or
> discriminators to FIU for testing the detector there. FIU will use
> their existing read-out electronics. We will send an MPOD and all
> cables that connect the ST-2s to the ST-3. We discussed how many signal
> cables need to be shipped (those running from the ST-3). We decided to
> defer a decision on that.
>
> We decided that we should do a test mechanical assembly at JLab before
> shipping the support structure to FIU, including as much as is
> practical: support ring to target support, ST-3 on installation cart,
> cables from ST-2 to ST-3, etc. The exact plan needs to be worked out.
>
> Schedule
>
> Werner laid out a very rough schedule given what we know now.
> 1. scintillators arrive at FIU: mid-May
> 2. scintillator testing and detector assembly done: end of June
> 3. Nick visit: early July
> 4. testing done: end of July
> 5. ship to JLab: mid-August
>
> Assembly Jig
>
> Eric presented the final design for the assembly jig. See his slides
> ([18]PDF, [19]Powerpoint) for details. Eric plans to call Chuck Hutton
> and discuss the design as well.
>
> Progress at McNeal
>
> [Added in press: Eric talked to Robert McNeal just after the meeting
> and sent in this report.]
>
> All 50 paddles have been inspected and have passed the initial QA
> check. Machining of the paddles has not yet commenced. They are waiting
> for the machines to finish other jobs. However, production should begin
> within a week.
>
> Robert quoted that the paddles will be shipped out to FIU, no later
> than 05/02/2014 which is right at the 4 week lead time we were quoted.
>
> Eric provided Robert with the most up to date mechanical drawing of the
> paddles. There were no substantial differences between the two drawings
> and this update will have no negative consequences.
>
> Robert mentioned that they do quantify the final dimensions of the
> paddles after they are machined. This is done both optically and by
> machine. Standard operating procedure dictates that they will only
> measure approximately 8 of the 50 paddles. He is willing to provide us
> with this data. It is possible for them to inspect all 50 paddles and
> provide us with their associated measurements for a minor inspection
> fee initially estimated at $200.00. Further discussions will be made
> regarding whether we should purchase this inspection data.
>
> References
>
> 18. https://halldweb1.jlab.org/talks/2014-2Q/Finalized_Assembly_Jig.pdf
> 19. https://halldweb1.jlab.org/talks/2014-2Q/Finalized_Assembly_Jig.pptx
>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: barbosa.vcf
Type: text/x-vcard
Size: 265 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/halld-pid/attachments/20140418/1122b0db/attachment-0002.vcf>
More information about the Halld-pid
mailing list