Hi Franz,

That will work great! Our plan is to prepare, disconnect and move all 
the electronics out of tagger hall  starting 9/8. This allows you 
additional time in case testing takes a little longer.

Thanks and best regards,
Fernando

On 8/21/2014 12:29 PM, Franz Klein wrote:
> For TAGH I would like to finish the cable connections downstream of the microscope and test the whole array using the installed electronics (at least using the CAEN-HV boxes). If possible, I'd like to do it some time next week.
>
> Greetings,
> Franz
>
> ----- Original Message -----
> From: "Richard Jones" <richard.t.jones at uconn.edu>
> To: "Alexander Somov" <somov at jlab.org>
> Cc: "Hall D beam working group" <halld-tagger at jlab.org>
> Sent: Thursday, August 21, 2014 12:19:02 PM
> Subject: Re: [Halld-tagger] Tagger hall plans
>
>
>
> In his last message, Alex Somov wrote:
>
>
> Richard should return the VXS crate, which we can install into the existing rack in the ESB.
>
>
>
> Will do. Can you provide us with enough lemo cables and a splitter to connect 15 outputs at a time to the crate, and read out both the fadc and tdc at the same time?
>
>
> -Richard J.
>
>
>
> On Thu, Aug 21, 2014 at 11:08 AM, Alexander Somov < somov at jlab.org > wrote:
>
>
>
> Hi Fernando,
>
> I tink that testing of TAGM should be done in the ESB. If the
> detector components are here in the beginning of September,
> it would take at least a week or two to assemble the TAGM. We
> may consider to move the detector to the Hall just to check that
> evrt fits and bring it back to the ESB.
>
> Richard should return the VXS crate, which we can install into
> the existing rack in the ESB. We'll need a control Wiener crate
> and some spare cables to read out one or two fadcs.
>
> Cheers,
> Alex
>
>
>
>
>
>
>
>
> On Thu, 21 Aug 2014, Richard Jones wrote:
>
>
>
> Fernando,
>
> I am going to propose that we set things up in the ESB area when we arrive,
> and do what setup and testing we can there prior to the move-in date in the
> first week of October or thereabouts. Any objections?
>
> -Richard Jones
>
>
> On Thu, Aug 21, 2014 at 10:03 AM, Fernando J Barbosa < barbosa at jlab.org >
> wrote:
>
>
>
> Hi Richard, Alex,
>
> We will start removing the electronics from the tagger hall on 22 Sept
> 2014 in preparation for beam on 29 Sept 2014. All the cables will be
> disconnected from the modules but remain in place with the mini-racks; we
> then remove the crates/chassis with the modules and move them to a safe
> place, probably the ESB.
>
> You have indicated that you will be bringing the TAGM to JLab during the
> week of 9/1. In view of this, you only have two weeks (weeks of 9/8 and
> 9/15) to install, connect and test the TAGM. Is this enough time to do any
> significant work (setup software, controls, readout, etc)? Or should we
> plan to work in the ESB, which allows limited testing (limited number of
> cables, no 208V for the crates so power is an issue anywhere outside of the
> tagger hall)?
>
> Please work out a viable plan and let me know ASAP. If we are not going to
> do anything in the tagger hall, we could go ahead and start removing the
> electronics earlier so we are not rushing later.
>
> Best regards,
> Fernando
>
>
>
>
> _______________________________________________
> Halld-tagger mailing list
> Halld-tagger at jlab.org
> https://mailman.jlab.org/mailman/listinfo/halld-tagger
>

-------------- next part --------------
A non-text attachment was scrubbed...
Name: barbosa.vcf
Type: text/x-vcard
Size: 265 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/halld-tagger/attachments/20140821/b2ec4617/attachment-0001.vcf 


More information about the Halld-tagger mailing list