GlueX Target Meeting, April 12, 2011
Minutes
Present: Hovanes Egiyan, Mark Ito, Chris Keith, Rory Miskimen, Tim
Whitlatch (chair), Elliott Wolin
* Tim brought along drawings and notes made two years ago, modeled on
the Hall B cryotarget.
+ We may need to pick Steve Christo's brain, especially about
lessons learned in Hall B.
+ The Hall B targets are Kapton, with DP190 epoxy joining the
seams. The scattering chambers are made of Rohacell.
+ We will have to perform pressure tests on the cells. Current
code may be more stringent than standards at the time the Hall
B targets were commissioned.
* The refrigerator will be bought in October or November.
+ The model being considered can liquify hydrogen starting from
room temperature, at about a liter per hour, corresponding to
15 watts at 20 K. Liquid hydrogen volume looks to be of order
a liter. Helium-4 will take longer to liquify.
+ The requirement that we want to be able to empty/fill the
target on the time-scale of a few hours (preferably less) was
restated.
+ The refrigerator have no cold moving parts.
* We will have to design and build the heat exchanger and heating
element. The refrigerator will stay on continuously and temperature
of the hydrogen controlled with a heater in the cold head.
* The gas panel can probably copied from that used by Q-Weak.
* Mechanical considerations
+ The target, its plumbing, and the refrigerator (including cold
head) will all be a "rigid body". Adjustment of the position
of the target on the beam line will be accomplished by
positioning the entire structure.
Items for the Next Meeting
* Chris will create a P&I diagram for the gas/refrigerator system
* Chris will distribute the manual for the refrigerator so others can
get started thinking about the relevant controls and monitoring.
* We will invite Steve to the next meeting.
* Next meeting in about a month.