[Halld] Run Coordinator report for November 7-14, 2018
Alexander Austregesilo
aaustreg at jlab.org
Fri Nov 16 16:05:17 EST 2018
Run Coordinator report for November 7-14, 2018
(from
https://halldweb.jlab.org/wiki/index.php/Run_Coordinator_report:_Fall_2018_w12)
The GlueX experiment in Hall D was scheduled for 152 hours of beam this
week, but received only 87.3 hours (57%). We could use about 80.8 hours
(ABU) or 53% of the scheduled beam time. Major causes for down time on
our side were a readout failure of the 5C11B beam position monitor
(~2h), a period during which our slow control system (CSS/EPICS) was not
responsive (~2h) and the scheduled installation of a new 10 inch beam
pipe for the Compton Calorimeter (~8h, during beam studies). The
remaining losses can be attributed to configuration changes. So far, the
experiment ran for 86% of the scheduled fall 2018 beam time and
collected 67% of the total data expected for this period.
This week was dedicated to a special measurement of cross sections at
lower energies in order to overlap with previous measurements from CLAS
and obtain a better understanding of systematic uncertainties. For this
purpose, the current in the PS magnet was reduced from 910A to 400A
which shifted the PS acceptance to the region between 3 and 5.5 GeV. The
tagger hodoscope counters in this energy region were turned on, which
limited the acceptable beam current to 40nA. We decided to take 40% of
the data with an amorphous radiator (trigger rate ~9kHz) and 60% with
the 47mum diamond radiator (trigger rate ~13kHz). For the latter, the
coherent edge was shifted down to 7GeV, producing a peak polarization
above 60%.
We started the low-energy program on Wednesday, when we recorded a TAC
run to determine the PS acceptance. Around 11pm, we started our first
low energy run and continued this program until Monday morning. Even
though the accelerator was down for more than 20 hours due to a HV issue
in RF cavity 1L23 over the weekend, we managed to collect 2.3B triggers
for the special low-energy data set while cycling through the different
radiator orientations 6 times. This corresponds to about 116% of the
previously defined goal.
The scheduled system recovery period on Monday was used for preparations
of the installation that was planned for Tuesday, for FCAL maintenance
and for investigations on the liquid hydrogen target. In addition, an
upgrade to Hall D current locks was performed. Unfortunately, the beam
was not available during the night. On Tuesday, a new beam pipe was
installed in preparation for the Compton Calorimeter for PrimEx. On
Tuesday evening, all settings were restored and the standard production
running was resumed.
Many thanks to the excellent shift crews and the commited experts on call!
Alex
More information about the Halld
mailing list