[Hbi-svt] [Fwd: SVT Module Construction Process]
Marc McMullen
mcmullen at jlab.org
Thu Jul 29 11:56:33 EDT 2010
Hi Michael,
I was wondering if you had a chance to look at these questions yet. We
met with Saptarshi today to try to get some firm numbers on the module
support and cooling, and hopefully engineering can start on the final
designs for these parts. I know that the answers to some of these affect
decisions on the designs for them, which will have some bearings on the
details of the electronics for me as well. We should still plan to meet
next Thursday.
Thanks
Marc
-------- Original Message --------
Subject: SVT Module Construction Process
Date: Wed, 21 Jul 2010 11:50:11 -0400
From: Marc McMullen <mcmullen at jlab.org>
To: Michael Merkin <merkinm at silab.sinp.msu.ru>
CC: HBI-SVT <Hbi-svt at jlab.org>, HBI <hbi-internal at jlab.org>
Hi Michael,
Last week we met with 12GeV upgrade management and went over the
progress of the project. By the end of the meeting we developed a list
of issues which need to be addressed, some of which we are hoping you
can help us out with the answers to. If you could review these perhaps
we can go over some of them in our bi-weekly EVO meeting tomorrow with
Latifa. Answers to these will help with the current progress and future
reviews and meetings.
The questions are as follows:
1. Is there any progress on evaluating the current MSU module
assembly process to allow for the current HFCB design?
2. Are there any previous experiments which use bolts/screws to
fasten the electronics to the module?
3. Are there any module construction tools which need to be purchased
or designed.
4. Using the proposed method of module construction (FR4 i-beams with
rohacell supports), what will provide for electromagnetic
shielding? Could you recommend any previous experiments using this
method?
5. If we do have to go with the carbon fiber/foam core design due to
the reasons of electromagnetic shielding and also prevention of
multiple scattering from the FR4 spacers, does MSU have the
capability to construct the stave?
6. What is the proposed module assembly process?
7. What mechanical designs are expected of Jefferson Lab to provide
for MSU?
8. When are you expecting any mechanical designs from Jefferson Lab?
9. Who will provide/order the module materials?
10. Which entity is expected to provide designs and parts/materials
for the module storage containers?
11. Is there any assistance we could provide that will allow for a
full chain test for the September review?
So far these are some of the questions we could use your help on, I'm
sure there will be more in the future.
Thanks,
Marc
-------------- next part --------------
A non-text attachment was scrubbed...
Name: mcmullen.vcf
Type: text/x-vcard
Size: 252 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/hbi-svt/attachments/20100729/553e34c4/attachment.vcf
More information about the Hbi-svt
mailing list