[Hbi-svt] Fwd: [Fwd: RFP# JSA-10-R289444, SVT Sensor Hamamatsu plans]
Peter Bonneau
bonneau at jlab.org
Fri Jun 11 12:04:05 EDT 2010
Hello Mitch,
We have reviewed Hamamatsu's comments and have answered their questions
below as you requested. Hamamatsu requires the following minor changes
in order for them to bid on the SVT sensors.
1) Increase of mask placement error by 1/2 of a micron. (1.5 to 2 microns).
2) They can not drop ship to MSU (Russia) directly.
3) After approval of 1st article sensor, increase production delivery
times by 6 weeks.
4) At least one extra week before RFP close.
Thanks,
Peter
Please respond to your parts as soon as you can. Send to me.
Mitch
RFP# JSA-10-R289444, Hamamatsu plans.eml
Subject:
RFP# JSA-10-R289444, Hamamatsu plans
From:
TBailey at hamamatsu.com
Date:
Fri, 11 Jun 2010 08:38:22 -0400
To:
Mitchell Laney <laney at jlab.org>
CC:
ehergert at hamamatsu.com
*Mitch, *
I have reviewed RFP# JSA-10-R28944 in detail with our factory and I want
JLabs to understand that Hamamatsu is interested in this opportunity and
business.
However, there are several technical and delivery requirements in the
RFP that Hamamatsu can not meet and these items are considered
non-negotiable by our side. The RFP instructions state that the Terms
and Conditions and technical specifications are minimum acceptable
values and the failure to meet or assent to these requirements
constitutes a deficiency. As a result, Hamamatsu must choose to "No
Bid" on this RFP unless JLabs can relax/modify the following requirements.
*1)* Technical Spec 5.6: We can not guarantee mask placement error <
1.5u. The best specification we can offer is < 2u. This item was
communicated to JLabs in the fall of 2009 and is non-negotiable.
Jefferson Lab modifies Specification B00000-01-01-S0001 Rev 6 - Silicon
Micro-Strip Sensors for the Hall B CLAS12 Silicon Vertex Tracker section
5.6. to < 2u (from the previous < 1.5 u - increase of 1/2 micron).
*2)* Technical Spec 5.16.b: We can not offer drop shipment to Russia
for any of the units under this RFP. This item is considered
non-negotiable.
Jefferson Lab will not require drop shipment to Russia.
*3)* Technical Specs 5.16 and JSA-200 (Delivery Requirements):
Hamamatsu can not meet the delivery schedule outlined for production
units. The current schedule does not allow for sufficient wafer
processing time after first article approval and the very best schedule
we could offer is as follows:
Jefferson Lab modifies technical Specs section 5.16 and JSA-200
(Delivery Requirements) to the following schedule:
*Qty*
*Type*
*Batch #*
*~Weeks after production approval*
~10% = 10pc/10pc/5pc
Hybrid/Intermediate/Far
1
10
~30% = 31pc/31pc/13pc
Hybrid/Intermediate/Far
2
14
~30% = 31pc/31pc/13pc
Hybrid/Intermediate/Far
3
18
~30% = 30pc/30pc/11pc
Hybrid/Intermediate/Far
4
22
If JLabs can relax the RFP requirements then Hamamatsu will choose to
bid on this project, however we will also likely require an extension of
at least 1wk to prepare all of the necessary materials and process the
RFP through our contracts review department. Therefore, we would also
like to request an extension.
The close date for Jefferson Lab RFP# JSA-10-R289444 has been modified
to June 30, 2010.
Please feel free to call me with any questions or concerns.
Regards,
Thomas Bailey
PHOTON IS OUR BUSINESS
South East Regional Sales Engineer
(P) 516.992.0137 | (F) 516-706-0412_
__http://sales.hamamatsu.com_ <http://sales.hamamatsu.com/>
*Mitchell Laney <laney at jlab.org>*
05/27/2010 11:07 AM
-------- Original Message --------
Subject: [Fwd: RFP# JSA-10-R289444, Hamamatsu plans]
Date: Fri, 11 Jun 2010 09:21:00 -0400
From: Mitchell Laney <laney at jlab.org>
To: Peter Bonneau <bonneau at jlab.org>
Please respond to your parts as soon as you can. Send to me.
Mitch
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/hbi-svt/attachments/20100611/5ddab285/attachment-0001.html
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 8382 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/hbi-svt/attachments/20100611/5ddab285/attachment-0001.jpe
-------------- next part --------------
An embedded message was scrubbed...
From: TBailey at hamamatsu.com
Subject: RFP# JSA-10-R289444, Hamamatsu plans