[Hps-ecal] commissioning update
    Nathan Baltzell 
    baltzell at jlab.org
       
    Tue Nov  4 21:10:33 EST 2014
    
    
  
Dear Everyone,
Working point calibration of Top LEDs was done this morning
(and a new signal cable problem found):
https://logbooks.jlab.org/entry/3303817
During which we noticed a new important issue:
https://logbooks.jlab.org/entry/3303943
The tripping HV groups are recorded here:
https://logbooks.jlab.org/entry/3303909
Summary of cosmic run status:
https://logbooks.jlab.org/entry/3303918
-Nathan, Holly, et.al ...
    
    