[Hps] run schedule and shift update

Nathan Baltzell baltzell at jlab.org
Wed Apr 8 19:44:59 EDT 2015


Hi Everyone,

The latest from the accelerator today is that the first possibility for beam to
Hall-B is now Tuesday, April 14.  These recent delays are due to some extra
efforts to understand what happened with the machine and the power outage
(ultimately resulting in loss of one CHL) for future knowledge before resuming
normal operations.

Hall-B shifts are now set to resume with day shifts on Tuesday, April 14th.
All shifts before then are cancelled.  Takashi Maruyama is the new RC.

-Nathan




On Apr 7, 2015, at 6:06 PM, Nathan Baltzell <baltzell at jlab.org> wrote:

> Hello All,
> 
> JLab is planning to deliver 1 GeV/pass beam, with Hall-B the priority hall, for the
> remainder of the Spring run until May 4.  Since there will be a lot of torus work in
> the hall, HPS may have to stick to nights and weekends next week.
> 
> The first possibility for beam to Hall-B is now delayed until day shift on Monday, April 13.
> All HPS shifts before then are cancelled.
> 
> Regards,
> Nathan
> 




More information about the Hps mailing list