[Hps] [EXTERNAL] Re: SLAC Holiday Power Shutdown
Omar Moreno
email at omarmoreno.net
Mon Dec 9 18:42:06 EST 2019
Hi,
After some discussion over the weekend on the impact of a 2 week shutdown
on lab activities, it was decided that maintenance of the substations will
be staged. As a result, the building housing all scientific computing will
remain on and *all computing services will be available *during the SLAC
winter shutdown.
Best,
--Omar Moreno
On Fri, Dec 6, 2019 at 11:31 PM Omar Moreno <email at omarmoreno.net> wrote:
> Hi,
>
> SLAC is planning to perform preventive maintenance of two substations
> during the winter shutdown one of which distributes power to the building
> housing all scientific computing. The planned shutdown is set to begin the
> evening of December 20th and will last through January 6th. During this
> time, nearly all computing services will be unavailable including the
> login nodes (e.g. rhel6-64), batch nodes, nfs and gpfs. Backup
> generators will be used to keep some essential services up during the
> shutdown including email.
>
> The backup generators will be tested during the week of December 16 and
> will cause an interruption of all computing services for a few hours. As
> soon as the date becomes concrete, I will forward along the details.
>
> Best,
>
> --Omar Moreno
>
>
>
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hps/attachments/20191209/5722744f/attachment.html>
More information about the Hps
mailing list