https://bluejeans.com/294836101?src=calendarLink

Dec. 14, 2020 – ERR, readiness review for 5kw irradiation
Dec. 15, 2020 – PSS certification for the LERF
Dec. 18 to Jan. 4 – Move dipole power supply from UITF to LERF
Jan. 5, 2021 – CHL2 goes to 2K
Jan 6 to 8, 2021 – Hot Check Out
Jan 11 to 15, 2021 – Isotope beam setup & run at 5kw

Topics for discussion:
1/4CM # 3 solenoid power supply; I had found a used replacement but it had the wrong option (480 VAC vs 208VAC) Sam found suitable replacement & it should arrive this week. Once it is installed we will need to go to power permit to check it out. Can this be brought to High Voltage for PSS cert on Tuesday w/o PS?

1X dipole move; the dipole needs to be moved 27mm, base plate does not have enough adjustment so it needs to be replaced, the option for the Jan. isotope run is to add additional horizontal correction - Steve will lead this discussion.

Hot Check Out first week after the break.

Thanks
Kevin

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20201209/18b101f2/attachment.html>


More information about the Isotope-prod mailing list