[Isotope-prod] No meeting today at 11:00
Kevin Jordan
jordan at jlab.org
Wed Oct 14 09:52:13 EDT 2020
Upcoming activities:
Rebuilding “raft” for 5 kilowatt exposure (photo below)
ERR approval for 5 kilowatt run (in progress)
LCLS-II clean room removal from LERF vault (this week?)
Re-install shield blocks (weather permitting Oct. 26)
Install new solenoid power supply for 1/4 CM #3 (power supply staged for install this week)
Gun check (date TBD)
1/4 CM #3 crowbar repair (early Nov.)
Re-install 1X duple power supply (Week of November 16)
Second stack exposure + 5 kilowatt 30 hour run (Week of November 30)
Any comments?
Thanks
Kevin
[cid:3FF97D6A-3FF4-48F2-BD99-5A12B956D7B5]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20201014/60f61a81/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: IMG_0353.jpeg
Type: image/jpeg
Size: 290663 bytes
Desc: IMG_0353.jpeg
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20201014/60f61a81/attachment-0001.jpeg>
More information about the Isotope-prod
mailing list