[Isotope-prod] LERF Update - Magnetron commissioning has begun!
Haipeng Wang
haipeng at jlab.org
Wed Dec 15 13:16:06 EST 2021
That is Great progress, Kevin. I was there yesterday late afternoon. I guess you still has a lot of low level PLC work. Do you need me to be with you tomorrow? I plan to be there for something else, but I can redirect my work for the LERF. If you are going to have RF power to generate, I need to bring RF power meter and spectrum analyzer to there too.
Haipeng
Get Outlook for iOS<https://aka.ms/o0ukef>
________________________________
From: Robert Rimmer <rarimmer at jlab.org>
Sent: Wednesday, December 15, 2021 12:52:25 PM
To: Kevin Jordan <jordan at jlab.org>; isotope-prod at jlab.org <isotope-prod at jlab.org>; LCLS II @ LERF <lerftest at jlab.org>
Cc: Haipeng Wang <haipeng at jlab.org>; Bonnie Rodriguez <bonnie at jlab.org>; Phillip Stanley <pstanley at jlab.org>; Tim Fitzgerald <tfitzger at jlab.org>
Subject: Re: LERF Update - Magnetron commissioning has begun!
awesome, thanks Kevin!
Bob.
________________________________
From: Kevin Jordan <jordan at jlab.org>
Sent: Wednesday, December 15, 2021 12:49 PM
To: isotope-prod at jlab.org <isotope-prod at jlab.org>; LCLS II @ LERF <lerftest at jlab.org>
Cc: Robert Rimmer <rarimmer at jlab.org>; Haipeng Wang <haipeng at jlab.org>; Bonnie Rodriguez <bonnie at jlab.org>; Phillip Stanley <pstanley at jlab.org>; Tim Fitzgerald <tfitzger at jlab.org>
Subject: LERF Update - Magnetron commissioning has begun!
The magnetron commissioning OSP is signed off, we had a walk through with Harry Fanning, Phillip Stanley, Bonnie Rodriguez, Billy Formichelli, Charlie Garrison, & myself. The locks were removed & breakers energized to the transmitter cabinet. The two 480 VAC breakers on the transmitter are both remote lever/cable actuated so, per procedure, there are no arc flash hazards when turning these levers ON/OFF as long as the main cabinet door is closed. Three of the four AVTs have been tested - the fourth is for the 480 VAC supply to the high voltage transmitter transformer & will be tested when all interlocks are satisfied. Next steps are to fill the cooling water circuits & test interlocks - if all goes well we should make some RF next week.
Thanks all for the support!
Kevin
[cid:AAC60375-E8FA-4A75-B497-72C56008A41B]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20211215/c9d57479/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: PastedGraphic-1.tiff
Type: image/tiff
Size: 576046 bytes
Desc: PastedGraphic-1.tiff
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20211215/c9d57479/attachment-0001.tiff>
More information about the Isotope-prod
mailing list