[Lerftest] Waveguide review slides posted
Jaroslaw Kowal
jkowal at jlab.org
Sat Oct 14 20:24:42 EDT 2017
Kevin,
It sounds good.
Please grab me after the meeting.
Jerry
From: "Kevin Jordan" <jordan at jlab.org>
To: "Joseph Gubeli" <gubeli at jlab.org>
Cc: "Jaroslaw Kowal" <jkowal at jlab.org>, "LCLS II @ LERF" <lerftest at jlab.org>
Sent: Friday, October 13, 2017 8:12:30 PM
Subject: Re: [Lerftest] Waveguide review slides posted
HI Jerry,
Let’s meet after the 8:00 meeting on Monday, we can go to the gallery and talk through the best path forward.
Kevin
Sent from my iPad
On Oct 13, 2017, at 11:40 AM, Joseph Gubeli < gubeli at jlab.org > wrote:
Hi Jerry,
Safety did an assessment and said that 18” is OK. This will leave 50” in the
aisle, they wanted a minimum of 48”. The SSA doors are easily removable with
an 18” gap. Kevin can talk about the other questions you have.
Cheers, Joe
From: Lerftest [ mailto:lerftest-bounces at jlab.org ] On Behalf Of Jaroslaw
Kowal
Sent: Friday, October 13, 2017 11:21 AM
To: Kevin Jordan < jordan at jlab.org >
Cc: LCLS II @ LERF < lerftest at jlab.org >
Subject: Re: [Lerftest] Waveguide review slides posted
Kevin,
I think by code you have to have 3 ft spacing.
Also with 18" spacing behind some of the SSAs you will not be able to open
the back door of SSA cabinet if access is need. These cabinets are 30" wide.
Is that a concern?
What I could do as an option is to install RF Interface chassis and
contactors in the rack.This would eliminate the need for the access to the
old racks.
In this case I'd need a floor space for additional rack.
A separate issue is power connections from PSS to SSAs.
What is the planned location of the PSS panel (assuming we'll go with this
solution)?
What are the planned cable paths?
Are you planning for cable trays etc.?
We might be more effective discussing these issues in person. Please set up
a meeting with interested parties if you think it's going to be
better/faster way.
Thank you,
Jerry
_____
From: "Kevin Jordan" < jordan at jlab.org < mailto:jordan at jlab.org > >
To: "Jaroslaw Kowal" < jkowal at jlab.org < mailto:jkowal at jlab.org > >
Cc: "LCLS II @ LERF" < lerftest at jlab.org < mailto:lerftest at jlab.org > >
Sent: Wednesday, October 11, 2017 5:22:29 PM
Subject: Re: [Lerftest] Waveguide review slides posted
Jerry,
Yes the tape is within an inch of final location, it looks to be 32”from the
rack to the SSA, is that enough?
Thanks
Kevin
Sent from my iPad
On Oct 11, 2017, at 5:11 PM, Jaroslaw Kowal < jkowal at jlab.org
< mailto:jkowal at jlab.org > > wrote:
Kevin,
I'd like to raise concern regarding the spacing behind the SSAs.
The first rack to the left of HPA houses PSS RF Interface chassis and cross
connects. Access to the front of this rack is required for PSS Certification
and in case of maintenance.
We'll have to check if there will be enough space to perform these duties.
Could someone estimate the spacing from the back of the SSA to this rack?
Can I depend on floor marking for this measurement?
Thank you,
Jerry
_____
From: "Kevin Jordan" < jordan at jlab.org < mailto:jordan at jlab.org > >
To: "LCLS II @ LERF" < lerftest at jlab.org < mailto:lerftest at jlab.org > >
Sent: Wednesday, October 11, 2017 3:58:54 PM
Subject: [Lerftest] Waveguide review slides posted
The LCLS-II waveguide layout review was held this AM, the slides have been
posted to the wiki:
https://wiki.jlab.org/lerf/index.php/Reviews
Comments and questions from the review will also be posted shortly.
Kevin
_______________________________________________
Lerftest mailing list
Lerftest at jlab.org < mailto:Lerftest at jlab.org >
https://mailman.jlab.org/mailman/listinfo/lerftest
BQ_BEGIN
<image001.png>
BQ_END
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/lerftest/attachments/20171014/c2156624/attachment.html>
More information about the Lerftest
mailing list