Kevin Jordan
jordan at jlab.org
Fri Jan 26 15:00:10 EST 2018
We have 15 of 16 Solid State Amps (SSA) delivered from SLAC. The remaining one will be here in ~ 6 weeks along with isolators & couplers.
Does anyone have an objection to Neil scheduling crane for next week to move them to the LERF gallery? He would also move the F100 CM to south access building.
We would then schedule the crane when additional LLRF & cryo racks arrive (Feb/March)
Have a nice weekend
Kevin