[Lerftest] LERF Lockup for Tuesday 3/5

Kevin Jordan jordan at jlab.org
Mon Mar 4 09:49:27 EST 2019


Thanks!
At the Wednesday meeting we will have a better idea how & when we will try for beam in the LEREF injector to the 0G dump.
Kevin


On Mar 4, 2019, at 8:47 AM, Will Oren <oren at jlab.org<mailto:oren at jlab.org>> wrote:

All,
Per Joe's direction that you would like to start activities in the LERF requiring Power Permit by 09:00 tomorrow, I have asked the Owl shift to lock up the vault before the end of their shift to avoid the morning rush that will come in MCC at the start of RF recovery/Hall accesses.

Please let your crews know that it will not be restricted access when they come in tomorrow morning unless you tell me that this won't work.

Will (PD for now)