[Moller] [EXTERNAL] MOLLER Director's Review Update
Mark L. Pitt
pitt at vt.edu
Mon Aug 24 10:30:57 EDT 2020
Dear MOLLER collaborators,
We are writing to give you an update on the CD-1 Director's Review of
the MOLLER Project that took place over the past week. The review took
place virtually this past Tuesday August 18 - Friday August 21 with both
plenary and breakout sessions.
The committee orally presented its responses to the charge questions,
comments, and two recommendations early on Friday afternoon. We attach
the answers to the charge questions. We will send out the full report
when we receive it after internal vetting. Some highlights of the oral
closeout in which the draft comments and recommendations were shared
included:
* Ed O'Brien's introductory comments indicated that the committee
thinks we are in good shape for CD-1 approval with some suggestions
for improvement. He said that we should all be very happy and proud
with what we have accomplished and hopefully even more proud about a
month from now.
* The response to all eight review charges was "Yes" with some
suggestions and references to comments for some of the items.
* The committee generated findings and comments for all four of the
Sub-Committee categories, and the comments were read orally during
the closeout. There were two recommendations: "The Project should
proceed to the OPA CD-1 Review" and "Prioritize the completion of
the design of the shielding due to its significant cost risk."
* Finally, the committee provided a two page list of suggestions to
improve the presentations and documentation in preparation for the
CD-1 review.
We will be reviewing the feedback from the committee and will be in
touch soon for help needed in preparation for the September 22 - 24 DOE
Independent Project Review.
We want to take this opportunity to give thanks for all the hard work
from the collaboration and project team over many years and the recent
review-directed preparation that have gotten us to this point. All the
presentations were outstanding and the physics leads and the CAMs
effectively demonstrated our work to date and the team’s overall
knowledge of the technical scope and the status of project planning.
We will continue to rely on your efforts as we look to success in the
next review and in the long run for the project as a whole.
Best regards,
KK, Jim, Mark
---------------------------------------
Mark Pitt
Department of Physics
Virginia Tech
Robeson Hall
Blacksburg, VA 24061-0435
Phone: (540) 231-3015
Fax: (540) 231-7511
e-mail: pitt at vt.edu
webpage: https://urldefense.proofpoint.com/v2/url?u=http-3A__www.phys.vt.edu_-7Epitt&d=DwIDaQ&c=CJqEzB1piLOyyvZjb8YUQw&r=k2-3YiXM4PG72x9M5ma_2Q&m=n3ajCfj7XOFxdnyAVKq907916NxkQ7547NGEZs0-j70&s=LaWJc0M9Vn7KPLmnzyHSOBeCChkv6tzwnoEFT39J9Js&e=
---------------------------------------
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/moller/attachments/20200824/c34b830b/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: MOLLER_DR_Charge_August2020_Final_wAnswers.pdf
Type: application/pdf
Size: 59387 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/moller/attachments/20200824/c34b830b/attachment-0001.pdf>