[Moller_L2] [EXTERNAL] Re: MOLLER review schedule
Krishna Kumar
kkumar at umass.edu
Wed Sep 21 11:11:59 EDT 2022
Hi, Michael. Jim is trying to navigate to a very complicated set of constraints to get us to the schedule we want for CD-3A and CD-2 approval, which is in turn critical to have us doing physics by the end of 2025.
I know this is going to be extraordinarily challenging and we will try to help you as much as possible to navigate the relevant reviews for the detectors while also participating in the test beam. We can discuss this in more detail at our next regular meetings or in separate chats.
Cheers,
KK
> On Sep 21, 2022, at 11:07 AM, Michael Gericke <Michael.Gericke at umanitoba.ca> wrote:
>
> Why can't it be moved to early December? Is it strictly necessary to have a Director's review every time we have a CD review? There are too many meetings and too little time to actually do the work we are getting reviewed about.
>
> Michael
>
> On 2022-09-21 10:05 a.m., James Fast wrote:
>>
>> Caution: This message was sent from outside the University of Manitoba.
>>
>> Michael,
>> I realize that many of these dates are not trivial to manage but there is not a better option that gets us to CD-3a review in January given the holidays.
>>
>> James Fast
>> MOLLER Project Manager
>> Jefferson Lab
>> 757-230-6833 (cell)
>> 757-269-5324 (office)
>>
>>
>> From: Moller_L2 <moller_l2-bounces at jlab.org> <mailto:moller_l2-bounces at jlab.org> on behalf of Michael Gericke <Michael.Gericke at umanitoba.ca> <mailto:Michael.Gericke at umanitoba.ca>
>> Date: Wednesday, September 21, 2022 at 11:02 AM
>> To: moller_l2 at jlab.org <mailto:moller_l2 at jlab.org> <moller_l2 at jlab.org> <mailto:moller_l2 at jlab.org>
>> Subject: [Moller_L2] [EXTERNAL] Re: MOLLER review schedule
>>
>> Hi Jim,
>>
>> The directors review is right before now scheduled beam test in Mainz. It is a very inconvenient time for that review! It will be hard enough to prepare (again on such short notice) for the beam test without then to also having to worry about the review.
>>
>> Thanks,
>>
>> Michael
>>
>> On 2022-09-21 9:42 a.m., James Fast wrote:
>>
>> Caution: This message was sent from outside the University of Manitoba.
>>
>> Now with attachment
>>
>> James Fast
>> MOLLER Project Manager
>> Jefferson Lab
>> 757-230-6833 (cell)
>> 757-269-5324 (office)
>>
>>
>> From: James Fast <jfast at jlab.org> <mailto:jfast at jlab.org>
>> Date: Wednesday, September 21, 2022 at 9:05 AM
>> To: MOLLER L2 <moller_l2 at jlab.org> <mailto:moller_l2 at jlab.org>, Ernest E Ihloff <eihloff at mit.edu> <mailto:eihloff at mit.edu>, James E Kelsey <jkelsey at mit.edu> <mailto:jkelsey at mit.edu>
>> Subject: MOLLER review schedule
>>
>> L2 and CAMs,
>> Attached are a few slides with the proposed schedule of activities for our various upcoming reviews. Please plan accordingly. I realize it is quite a busy schedule, but it is the final push to get to constructing MOLLER.
>>
>> Jim
>>
>> James Fast
>> MOLLER Project Manager
>> Jefferson Lab
>> 757-230-6833 (cell)
>> 757-269-5324 (office)
>>
>>
>>
>> _______________________________________________
>> Moller_L2 mailing list
>> Moller_L2 at jlab.org <mailto:Moller_L2 at jlab.org>
>> https://mailman.jlab.org/mailman/listinfo/moller_l2 <https://mailman.jlab.org/mailman/listinfo/moller_l2>_______________________________________________
> Moller_L2 mailing list
> Moller_L2 at jlab.org
> https://mailman.jlab.org/mailman/listinfo/moller_l2
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/moller_l2/attachments/20220921/8ebb2d02/attachment-0001.html>
More information about the Moller_L2
mailing list