Colleagues,

Thank you for taking the time to attend my update meeting. Again, we will continue to meet up until the start of the SAM. For those who couldn't make the meeting and/or are just interested, here is the link to the video recap: Recap: SAM25 update meeting [hybrid] Thursday, August 7 | Meeting | Microsoft Teams<https://teams.microsoft.com/l/meetingrecap?driveId=b%21FKCfEtqw0kCxS-p-uZP0j56Q_9wtVHJGhVdO-NkAnc7edGtCgQWUTpDAGr9iFURO&driveItemId=01WBAZBAHU3V7GJK6NQ5C2INVXBZFCN73F&sitePath=https%3A%2F%2Fjeffersonlab-my.sharepoint.com%2F%3Av%3A%2Fg%2Fpersonal%2Ffrierson_jlab_org%2FEfTdfmSrzYdFpDa3Dkom_2UB7vZEnzuxKxCfU_lhJ6_9zg&fileUrl=https%3A%2F%2Fjeffersonlab-my.sharepoint.com%2F%3Av%3A%2Fg%2Fpersonal%2Ffrierson_jlab_org%2FEfTdfmSrzYdFpDa3Dkom_2UB7vZEnzuxKxCfU_lhJ6_9zg&iCalUid=040000008200e00074c5b7101a82e008000000005dc168a95105dc01000000000000000010000000585b9e1fdd2223409dbda502344046d6&threadId=19%3Ameeting_OTQyNzE5MDItZWJjNS00ZGI1LTk3ZTMtMDZhYzQzMzM5NDA3%40thread.v2&organizerId=aa8d2117-8468-4ac4-be98-e2b85c220410&tenantId=b4d7ee1f-4fb3-4f06-9037-2b5b522042ab&callId=9260cd8c-a353-4618-ba50-4e8c2bcfd2d5&threadType=Meeting&meetingType=Scheduled&subType=RecapSharingLink_RecapChiclet>
Let me know if anyone is having trouble viewing it. The slideshow is attached also.

Some points to note from this meeting:

  *
To connect ATLis to an ePAS permit (from the permit), it cannot be in "Planning Complete" and above. However, if it is, the author can bring it back to the "Planning" stage to make the connection.
  *
The Pre-SAM safety briefing will occur on 2-Sept. More info to come.
  *
The massive LOTO of 3-Sept will look a little different this year.
     *
Groups who will need to work in and around magnet leads in the tunnel, should plan on witnessing the DCP LOTO (voltage verification) on 3-Sept. The same could apply to the RF CPS equivalent if working in and around those supplies.
        *
I think submitting a plan on how this is going to go will be beneficial to all participating.
     *
We will have observers from multiple departments at the LOTO activity. They include (but not limited to)
        *
Quality Assurance
        *
EHS
        *
DOE site office
     *
This looks like "ProActive" event from the last SAM. For our groups that will be executing LOTOs on that day, please keep this in the back of your mind as you are planning. Lastly, please speak up with questions and concerns about this so they can be addressed.
     *
RadCon will be spending most of 3-Sept performing surveys. Service buildings may not be deposted until 4-Sept.
     *
There was an updated made concerning pre-job briefs (PJB). The Management Safety Discussion (MSD) tool now contains a link to the PJB checklist:

[cid:3d0ba5e1-5413-4992-96ad-14f75344c22c]

When filling out this form, it seems one only needs to satisfy the areas that are starred. Thanks to the representatives from EHS for being present to address our questions and concerns.

That is all I have for now. Any other questions/concerns and/or updates to your plans for the SAM can be sent to me and we can address it.

See you next week.

Shawn


________________________________
From: Shawn Frierson
Sent: Thursday, August 7, 2025 15:35
Cc: monday_1330 at jlab.org <monday_1330 at jlab.org>; Steve Hardisty <hardisty at jlab.org>; Lanitra Butler <lbutler at jlab.org>; Riad Suleiman <suleiman at jlab.org>; Mike Bristow <bristow at jlab.org>; Mike Bevins <mbevins at jlab.org>; Todd Alther <alther at jlab.org>; Roger Ruber <ruber at jlab.org>; Adam Duzik <duzik at jlab.org>; Nate Andrews <nandrews at jlab.org>; Adam Cutler <cutler at jlab.org>; Bamunuvita Gamage <randika at jlab.org>; Brandon Richardson <brandonr at jlab.org>; Tilya Jones <tilya at jlab.org>; Maxwell Roy <maxwellr at jlab.org>; Christopher Keith <ckeith at jlab.org>; Scott Bruhwel <sbruhwel at jlab.org>; Tomasz Plawski <plawski at jlab.org>; Nathan Rider <nrider at jlab.org>; Jerry Kowal <jkowal at jlab.org>; Anne Payne <apayne at jlab.org>; Jason Joyce <jjoyce at jlab.org>; Scott Higgins <higgins at jlab.org>; Christine Snetter <snetter at jlab.org>; Abdulmalik Ismail <aismail at jlab.org>; Omar Garza <garza at jlab.org>; William Baumgartner <wbaum at jlab.org>; Erik Werlau <werlau at jlab.org>; David Hamlette <hamlette at jlab.org>; Jennifer Williams <jennifer at jlab.org>; John Riesbeck <riesbeck at jlab.org>
Subject: SAM25 update meeting [hybrid]
When: Thursday, August 14, 2025 2:00 PM-3:00 PM.
Where: MCC Conference Room


 With the SAM set to begin and month from now (03-Sept.), we should be starting to finalize our plans concerning what tasks are to be conducted before the start of the new year when we will be gearing up restart the machine for an new Physics run. These last meetings will be used as a forum for any questions one may have about the SAM and/or specific tasks one is involved in. I also want to speak a little more about ATLis.



Feel free to forward this to anyone who didn't receive an invite.



Meeting Agenda:



More ATLis tidbits - start submitting ATLis entries now!

Updates from last meeting

Questions/concerns about supporting CM moves/upgrades

Questions/concerns about what will happen on 03-Sept

AOB



See you on Thursday.

________________________________________________________________________________

________________________________________________________________________________

Microsoft Teams Need help?<https://aka.ms/JoinTeamsMeeting?omkt=en-US>

Join the meeting now<https://teams.microsoft.com/l/meetup-join/19%3ameeting_OTQyNzE5MDItZWJjNS00ZGI1LTk3ZTMtMDZhYzQzMzM5NDA3%40thread.v2/0?context=%7b%22Tid%22%3a%22b4d7ee1f-4fb3-4f06-9037-2b5b522042ab%22%2c%22Oid%22%3a%22aa8d2117-8468-4ac4-be98-e2b85c220410%22%7d>

Meeting ID: 273 151 501 130 7

Passcode: HB3TQ7B3

________________________________

For organizers: Meeting options<https://teams.microsoft.com/meetingOptions/?organizerId=aa8d2117-8468-4ac4-be98-e2b85c220410&tenantId=b4d7ee1f-4fb3-4f06-9037-2b5b522042ab&threadId=19_meeting_OTQyNzE5MDItZWJjNS00ZGI1LTk3ZTMtMDZhYzQzMzM5NDA3@thread.v2&messageId=0&language=en-US>




________________________________________________________________________________







________________________________________________________________________________

Microsoft Teams Need help?<https://aka.ms/JoinTeamsMeeting?omkt=en-US>

Join the meeting now<https://teams.microsoft.com/l/meetup-join/19%3ameeting_OTUwZGIxMWQtNzBlMS00YTgyLTk5MmQtOTRiNTA3MWU4NTE2%40thread.v2/0?context=%7b%22Tid%22%3a%22b4d7ee1f-4fb3-4f06-9037-2b5b522042ab%22%2c%22Oid%22%3a%22aa8d2117-8468-4ac4-be98-e2b85c220410%22%7d>

Meeting ID: 224 227 180 603 6

Passcode: NW33Xj3G

________________________________

For organizers: Meeting options<https://teams.microsoft.com/meetingOptions/?organizerId=aa8d2117-8468-4ac4-be98-e2b85c220410&tenantId=b4d7ee1f-4fb3-4f06-9037-2b5b522042ab&threadId=19_meeting_OTUwZGIxMWQtNzBlMS00YTgyLTk5MmQtOTRiNTA3MWU4NTE2@thread.v2&messageId=0&language=en-US>




________________________________________________________________________________
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/monday_1330/attachments/20250815/82c377f6/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image.png
Type: image/png
Size: 45702 bytes
Desc: image.png
URL: <https://mailman.jlab.org/pipermail/monday_1330/attachments/20250815/82c377f6/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Pre-SAM_brief(13-Aug).pdf
Type: application/pdf
Size: 89849 bytes
Desc: Pre-SAM_brief(13-Aug).pdf
URL: <https://mailman.jlab.org/pipermail/monday_1330/attachments/20250815/82c377f6/attachment-0001.pdf>


More information about the Monday_1330 mailing list