Concrete stoops will be constructed at the exterior exit doors for wings 
A, B & C of CEBAF Center.
These exit doors will remain closed during construction, except for 
emergency exit, and all personnel will need to use other doors to enter 
and exit the building.
The construction is scheduled to start on Thursday, Sept. 1 and will be 
completed by Monday, Sept. 5, subject to weather.
If you have any questions, please call or page Suresh Chandra of 
Facilities Management at x7248.