Allen,
I just realized you requested that the updated version be emailed instead of uploaded. I have added the updated version to this email. Please disregard the updated version in the Ready for Approvals folder.
Thank you,
Tiffany Ganey
From: Tiffany Ganey
Sent: Wednesday, April 28, 2021 8:24 AM
To: Allen Samuels <samuels at jlab.org>; Tom Powers <powers at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: RE: New DocuShare document routing task (Step 1 Completion): PLACLN-PR-VSA-CAV-CCAL.docx
Comments have been incorporated. Both steps 7.4 and 9.4 were revised to read “about -20 dB”. I also added the general warning from PLACLN-PR-VSA-CAV-MODE on the VTA/VSA radiation area. The updated procedure PLACLN-PR-VSA-CAV-CCAL has been added to the Ready for Approvals folder. Please delete the current / disapproved version, move the updated procedure to the Approvals folder, and send the updated procedure version out for approval.
New step 2.2 added and subsequent steps renumbered: The VTA / VSA is a radiation area when high power tests are being performed. In addition to flip signs indicating a change in state, the magenta beacons each shield lid are an indication that high power operation is enabled. Individuals who are not approved to be in the VTA / VSA during high power operation as per the VTA RWP are required to leave the area during high power testing.
Tiffany Ganey
From: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Sent: Tuesday, April 27, 2021 4:07 PM
To: Tiffany Ganey <ganey at jlab.org<mailto:ganey at jlab.org>>
Cc: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: FW: New DocuShare document routing task (Step 1 Completion): PLACLN-PR-VSA-CAV-CCAL.docx
Tiffany,
This procedure has been approved. Please make the changes noted below, and send the revised procedure to pansophy at jlab.org<mailto:pansophy at jlab.org>. From there, I will upload the correct version.
Thank you for your time,
Allen
From: DocuShare Workflow <docushare at jlab.org<mailto:docushare at jlab.org>>
Sent: Tuesday, April 27, 2021 3:55 PM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Subject: New DocuShare document routing task (Step 1 Completion): PLACLN-PR-VSA-CAV-CCAL.docx
You have a new DocuShare document routing task:
Subject: PLACLN-PR-VSA-CAV-CCAL.docx
Date: 04/27/2021 15:54:32
New revision with Tiffany's revisions
Step 1 Completion:
Tiffany Ganey, 04/09/2021 12:24:40 Approved:
Natalie Brock, 04/09/2021 14:29:39 Approved:
Tom Powers, 04/27/2021 15:54:30 Approved:
7.4 should the directivity be about -20 dB?
Approved after the minor change.
Tony Reilly, 04/12/2021 11:35:32 Approved:
To view your pending document routing tasks, click on the link below to login to DocuShare:
https://jlabdoc.jlab.org/docushare/dsweb/routing/routing_email.jsp?url=report_base.jsp&reportType=ForApprovalCompletion&routingSlipRequestID=17413¬ifyID=17424&workFlowJobName=17413
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210428/1ef24e05/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: PLACLN-PR-VSA-CAV-CCAL.docx
Type: application/vnd.openxmlformats-officedocument.wordprocessingml.document
Size: 1193651 bytes
Desc: PLACLN-PR-VSA-CAV-CCAL.docx
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210428/1ef24e05/attachment-0001.docx>
More information about the Pansophy
mailing list