[Pansophy] HE VTRF traveler status? (STATUS of L2HE travelers for Cavities) PLEASE REVIEW THE REQUESTS

Valerie Bookwalter bookwalt at jlab.org
Fri Apr 30 11:39:16 EDT 2021


Liang,

Please do not enter any new data into the L2PRD project area.

Allen is working on getting the L2HE-VTA-CAV-VTRF traveler into the system,
even though Ari has NOT yet approved the document.

We have received the L2HE-VTA-CAV-COOL traveler and it will be processed soon.
We have not received any other documents, but we have received this request from Tiffany and we are working through this list. If you know who the authors are supposed to be, then let them know we are waiting and working on this.

Process Step
L2HE Traveler ID
Based on Traveler
L2HE Traveler Status
Comments
RF Inspection
L2HE-TUNE-CAV-RFIN

Issued
for as-received from vendor; use D3 for refurbishment cavities
CMM
L2HE-INSP-CAV

Issued
for as-received from vendor; use D3 for refurbishment cavities
Dual USC (Liquinox + DI)
L2HE-CHEM-CAV-USC
C100R-CAV-CHEM-USC
Draft needed based on C100R

2-pass HPR
L2HE-CHEM-CAV-HPR
C100R-CAV-CHEM-HPR
Draft needed based on C100R

First Assembly (FP, FPC, HOM)
L2HE-CLNRM-CAV-FRST
L2PRD-CAV-ASSY-FRST
Draft needed based on L2PRD

Second Assy
L2HE-CLNRM-CAV-SCND
L2PRD-CAV-ASSY-SCND
Draft needed based on L2PRD

Transfer to Test Stand
L2HE-CLNRM-CAV-TSTD and L2HE-CLNRM-CAV-TSTD-D5
L2PRD-CAV-TRANS-TSTD and L2PRD-CAV-TRANS-TSTD-D5
Draft needed based on L2PRD

Cooldown to 2K (including sensor install and checkout)
L2HE-VTA-CAV-COOL
L2PRD-CAV-VTA-COOL
Justin has draft; needs to be uploaded to DocuShare
L2PRD parameters need to be updated for L2HE
VTRF
L2HE-VTA-CAV-VTRF
L2PRD-CAV-VTRF
In Approvals
L2PRD parameters need to be updated for L2HE
HOM Survey
L2HE-VTA-CAV-HOM
L2PRD-CAV-VTA-HOM
Draft needed based on L2PRD


From: Pansophy <pansophy-bounces at mailman.jlab.org> On Behalf Of Liang Zhao
Sent: Friday, April 30, 2021 9:00 AM
To: pansophy <pansophy at jlab.org>
Cc: Peter Owen <powen at jlab.org>
Subject: Re: [Pansophy] HE VTRF traveler status?

Oh, and the HOM survey traveler (L2PRD-CAV-VTA-HOM) usually go together with VTRF traveler. So it probably will go the same path with VTRF traveler.

Liang
________________________________
From: Liang Zhao
Sent: Friday, April 30, 2021 8:56 AM
To: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Cc: Peter Owen <powen at jlab.org<mailto:powen at jlab.org>>
Subject: HE VTRF traveler status?

Hi Pansophy team,

I heard from Ari that the HE cavity vertical testing (VTRF) traveler will be copied from L2PRD (L2PRD-CAV-VTRF)? Is that the plan? I have a HE cavity testing result to put in Pansophy. If HE traveler is not going to be ready for a while, I may just put it in L2PRD for now.

Thanks,
Liang
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210430/5e692117/attachment-0001.html>


More information about the Pansophy mailing list