[Pansophy] FW: L2HE Travelers for 2Phase and Vacuum Equipment
Allen Samuels
samuels at jlab.org
Thu Jul 15 11:17:13 EDT 2021
Some updates on the L2PRD travelers in the L2HE masterlist
Allen
From: Adam O'Brien <aobrien at jlab.org>
Sent: Thursday, July 15, 2021 10:52 AM
To: Katherine Wilson <kwilson at jlab.org>; Allen Samuels <samuels at jlab.org>
Cc: John Fischer <fischer at jlab.org>
Subject: Re: L2HE Travelers for 2Phase and Vacuum Equipment
Sorry, I accidentally sent that email before it was done.
There is one more light-red traveler which is my responsibility, which is L2PRD-CM-INSP-MCCLA. This was for the MC-pumping lines, which have already been received and did have a paperwork package but Mike has already taken care of it. They were inspected by Meyer so I don't think we need to do any additional inspection. That can be removed from the list also.
Thank you,
Adam O'Brien
Staff Engineer, SRF Operations
600 Kelvin Drive
Suite 8, Mailstop 55-H
Newport News, VA 23606-4323
Cell: (513)290-3210
________________________________
From: Katherine Wilson <kwilson at jlab.org<mailto:kwilson at jlab.org>>
Sent: Thursday, July 15, 2021 10:34 AM
To: Adam O'Brien <aobrien at jlab.org<mailto:aobrien at jlab.org>>; Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Cc: John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>
Subject: Re: L2HE Travelers for 2Phase and Vacuum Equipment
Sounds reasonable. Adding John for his information.
________________________________
From: Adam O'Brien <aobrien at jlab.org<mailto:aobrien at jlab.org>>
Sent: Thursday, July 15, 2021 10:32 AM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Cc: Katherine Wilson <kwilson at jlab.org<mailto:kwilson at jlab.org>>
Subject: L2HE Travelers for 2Phase and Vacuum Equipment
According to my co-TR, all QC inspections have been performed on everything for 2-Phase prior to them shipping from Fermi, so there should no receiving inspections required on our end. There will be some items that will need a receiving traveler to handle paperwork, but I'm (still) waiting to hear back on which parts thos will be. Assuming that travelers which only need receiving paperwork do NOT need to be on the master traveler list, the following can be removed:
L2HE-INSP-IROD2L
L2HE-INSP-IROC2P
In the light-red highlighted area at the end of the Inspection/Inventory section, the following fall under my responsibility:
2-Phase (No receiving inspection required, may or may not need a receiving traveler for QC paperwork)
L2PRD-CM-INSP-BP2PH
L2PRD-CM-INSP-LLDS
L2PRD-CM-INSP-LLNDS
L2PRD-CM-INSP-LLNUS
L2PRD-CM-INSP-LLUS
L2PRD-CM-INSP-PEC2P
Adam O'Brien
Staff Engineer, SRF Operations
600 Kelvin Drive
Suite 8, Mailstop 55-H
Newport News, VA 23606-4323
Cell: (513)290-3210
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210715/a626d8a8/attachment.html>
More information about the Pansophy