Mike and Anne,
Yes all C75 cavities have a different shape and design. The end groups however are the same for both projects.
Kurt
________________________________
From: Mike Dickey <mdickey at jlab.org>
Sent: Thursday, May 27, 2021 10:41 AM
To: E. Anne McEwen <mcewen at jlab.org>; Valerie Bookwalter <bookwalt at jlab.org>; George DeKerlegand <georged at jlab.org>; Kurt Macha <macha at jlab.org>
Cc: pansophy at jlab.org <pansophy at jlab.org>
Subject: RE: C50R-CPR-INSP-CAV-R3
Hi Anne,
I know that the end groups have been cut off of some “old” cavities and sent to the vendor for “new” cavity assemblies. However I do not know the designs of the cavities before and after. Kurt may be able to shed some light on this topic for clarity.
Mike Dickey
SRF Inventory Technician
Jefferson Lab
12000 Jefferson Ave
Newport News, VA 23606
(757) 269-7755
From: Pansophy <pansophy-bounces at mailman.jlab.org> On Behalf Of E. Anne McEwen
Sent: Thursday, May 27, 2021 10:18 AM
To: Valerie Bookwalter <bookwalt at jlab.org>; George DeKerlegand <georged at jlab.org>; Kurt Macha <macha at jlab.org>
Cc: pansophy at jlab.org
Subject: Re: [Pansophy] C50R-CPR-INSP-CAV-R3
Hi Valerie
The cavity shape of C75 vs C50 are different – I am guessing this may drive the par to have slight differences also – assuming this the case then likely we will need separate C50 vs C75 Pair travelers
We will likely be doing the pair next week so important that we clear this up – I am putting Kurt Macha on Copy
Thanks Anne
From: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Sent: Thursday, May 27, 2021 9:41 AM
To: George DeKerlegand <georged at jlab.org<mailto:georged at jlab.org>>
Cc: E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>; pansophy at jlab.org<mailto:pansophy at jlab.org>
Subject: C50R-CPR-INSP-CAV-R3
Aaron,
I understand you are asking about the C50R-CPR-INSP-CAV-R3 traveler.
Does this traveler also exist under the C75 project?
We are trying to move ALL Inspections into the C75 project area in preparation for the ER5C project move occurring this summer.
The ER5C (Energy Reach 5 Cell) Project will house a single set of INSP / CHEM / FURN / etc travelers for both the C50R and C75 travelers in order to accommodate the “common parts” between the 2 projects.
Valerie Bookwalter
Jefferson Lab, SRF Department
Pansophy Team
1-757-813-6716 (CELL)
1-767-269-5802 (OFFICE – currently working offsite)
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210527/f99cb6ce/attachment.html>
More information about the Pansophy
mailing list