[Pansophy] Rework Done: NCR:530 on SNSPPU-CLNRM-CST-LEAK-R1--7

Valerie Bookwalter bookwalt at jlab.org
Tue Jun 14 20:23:33 EDT 2022


Justification please to put in comment

From: Pansophy <pansophy-bounces at mailman.jlab.org> On Behalf Of Megan McDonald
Sent: Tuesday, June 14, 2022 7:43 PM
To: pansophy <pansophy at jlab.org>
Subject: Re: [Pansophy] Rework Done: NCR:530 on SNSPPU-CLNRM-CST-LEAK-R1--7

Val,
Is this something you wanted us to ask for justification on?
I believe this is the one that started as a D3

From: Pansophy <pansophy-bounces at mailman.jlab.org<mailto:pansophy-bounces at mailman.jlab.org>> On Behalf Of Naeem Huque
Sent: Monday, June 13, 2022 10:15 AM
To: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: [Pansophy] Fw: Rework Done: NCR:530 on SNSPPU-CLNRM-CST-LEAK-R1--7

Hello,

Could you please re-open this NCR

Thanks,
Naeem
________________________________
From: FOREHAND at JLAB.ORG<mailto:FOREHAND at JLAB.ORG> <FOREHAND at JLAB.ORG<mailto:FOREHAND at JLAB.ORG>>
Sent: Monday, June 13, 2022 8:22 AM
To: Danny Forehand <forehand at jlab.org<mailto:forehand at jlab.org>>
Cc: Ed Daly <edaly at jlab.org<mailto:edaly at jlab.org>>; Naeem Huque <huque at jlab.org<mailto:huque at jlab.org>>; Danny Forehand <forehand at jlab.org<mailto:forehand at jlab.org>>; Juan Jordan <jjordan at jlab.org<mailto:jjordan at jlab.org>>
Subject: Rework Done: NCR:530 on SNSPPU-CLNRM-CST-LEAK-R1--7


An Staff/Technician has reworked Non-Conformance Report - sequence number 530 for traveler SNSPPU-CLNRM-CST-LEAK-R1--7.
PAGE 3: MODIFICATION/RE-MEASURE
Rework Staff:
JJORDAN
JJORDAN
FOREHAND
Rework Date:
15-May-2022
17-May-2022
20-May-2022
Rework Comment:
15May2022 Bagged bellow joints between cav 2 and 3 separately to purge with nitrogen and identify leak. Cav 2 downstream leak sized at 4.96e-06 Torr L/s Cav 3 upstream no leak detected. Started bagging Cav 1 and 2 section. 16May2022 Finished bagging between Cav 1 and 2. Purging bellows with nitrogen while spraying one FPC at a time with He. Cav 1 FPC no leak detected. Cav 2 FPC Leak sized at 1.28e-07 Torr L/s. After allowing scan to recover started with Cav 1 downstream bellows no leak detected. Cav 2 upstream bellows leak sized at 3.98e-09 Torr L/s. Increased torque for all 3 flanges to 35 ft lbs. Cav 2 downstream bellows now at 1.06e-06 Torr L/s. Cav 2 upstream bellows now at 2.67e-09 Torr L/s. Cav 2 FPC no leak visible.
17May2022 Increased torque on Cav 2 upstream and downstream to 40 ft lbs. Cav 2 downstream bellows now at 4.41e-07 Torr L/s. Cav 2 upstream bellows now at 3.4e-09 Torr L/s. Increased torque on Cav 2 upstream and downstream to 45 ft lbs. Cav 2 downstream bellows now at 3.6e-07 Torr L/s. Cav 2 upstream bellows now at 4.12e-09 Torr L/s String isolated to swap over to slow bleed up line. Slow bleed up started at 2:06pm.
18May2022 Gasket changed on Cav 2 upstream 19May2022 Bellows changed between Cav 2-3. Slow pump down started. 20May2022 Leak in bag 3 sized at 1.72e-08 Torr L/s. Leak in bag 4 sized at 3.49e-09 Torr L/s. Bagged Cav 2-3 bellows individually as well as Cav 2 upstream and FPC. Started narrowing leaks down after lunch. Cav3 upstream no leak visible after 5 mins of helium spray. Cav2 downstream leak sized at 1.35e-08 Torr L/s. Cav2 upstream leak sized at 3.05e-09 Torr L/s. Cav 2 FPC leak sized at 3.27e-11 Torr L/s. Increased torque on Cav2 upstream and downstream to 50ft lbs. Cav2 downstream no leak detected. Cav2 upstream no change.
Verify Staff:
FOREHAND
FOREHAND
JJORDAN
Verify Date:
15-May-2022
17-May-2022
20-May-2022
Verify Comment:




ENGINEER RESPONSE
Response Engr:



Response Date:



Disposition:
Hold/Modify
Disposition Comment:



PAGE 2: FIRST DISPOSITION
Response Engr:
FOREHAND
Response Date:
08-Jun-2022
Disposition:
Hold/Modify
Disposition Comment:
Try to improve leaks to an acceptable rate before turning over string to CMA.

PAGE 1: INITIATE AND DESCRIBE
SN:
PPU-06
SNtype:
CSTSN
DRAWING NUM:
104211500-M8U-8200-A001
PART DESCRIPTION:
CRYO STRING ASSEMBLY
TRAV_ID:
SNSPPU-CLNRM-CST-LEAK
TRAV_REV:
R1
TRAV_SEQ_NUM:
7
DESCRIBE STAFF:
FOREHAND
DESCRIBE DATE:
2022-06-08 15:18:00.0
DESCRIBE COMMENT:
The total leak rate of the string is higher than the specified 3E-10 Torr l/s. The first leak is approx. 3.3E-6 Torr l/s. The second is approx. 6.5E-8 Torr l/s.
NOTIFICATION COMMENT:


The NCR is at the following URL: 530<https://pansophy.jlab.org/pansophy/Travelers/TRAVELER_FORM.cfm?project=SNSPPU&area=SNSPPU&system=CLNRM&TRAV_ID=SNSPPU-NCR&TRAV_REVISION=R12&page=3&maxpage=4&TRAV_SEQ_NUM=530&travstat=&serialnum=PPU-06&SN=PPU-06&SNTYPE=CSTSN>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20220615/844a7d5c/attachment.html>


More information about the Pansophy mailing list