Forgot to tag pansophy in this. Whoops

From: Allen Samuels
Sent: Monday, March 21, 2022 1:55 PM
To: Tiffany Ganey <ganey at jlab.org>; Danny Forehand <forehand at jlab.org>; Peter Owen <powen at jlab.org>; John Hogan <hogan at jlab.org>
Subject: FW: New DocuShare document routing task (Step 1 Completion): L2HE-CLNRM-CST-ASSY-R1.docx

The L2HE-CLNRM-CST-ASSY-R1 traveler has been approved and uploaded to pansophy.

Allen

From: DocuShare Workflow <docushare at jlab.org<mailto:docushare at jlab.org>>
Sent: Tuesday, March 15, 2022 1:23 PM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Subject: New DocuShare document routing task (Step 1 Completion): L2HE-CLNRM-CST-ASSY-R1.docx

You have a new DocuShare document routing task:

Subject: L2HE-CLNRM-CST-ASSY-R1.docx
Date: 03/15/2022 13:23:14

Step 1 Completion:

Tiffany Ganey, 03/14/2022 08:54:23 Approved:

Danny Forehand, 03/15/2022 13:23:14 Approved:

Peter Owen, 03/14/2022 16:20:31 Approved: From a purge system perspective, this traveler is correct in its procedure and terminology. I cannot speak to torque values or other stages of assembly. -Peter

John Hogan, 03/13/2022 13:24:30 Approved:
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20220321/237a7259/attachment.html>


More information about the Pansophy mailing list