[PEPPo] Last day for tunnel access...

Joseph Grames grames at jlab.org
Tue Nov 1 08:45:43 EDT 2011


Hi Folks,

fyi - Notwithstanding requests to the PD, today is the last scheduled 
day to be in the tunnel.  Operations plans to lock up around 4pm today 
and ideally stay locked up.  Of course, there will be accesses, but 
they'll be limited and need priority.

What does this mean?   Please....

1. *Mark/Kent* - Good idea to remove any hardware you no longer need in 
tunnel.  Plug the IA back in?

2. *Jim* - Make measurements you need to fabricate the plastic boxes for 
magnet leads.  I'll take  photos too.

3. *Steve/Wes* - Stow or remove any remaining radiation monitor parts 
that aren't being used

4. *Reza* - Put A2 back, leave it as is, put some label or tape so not 
inadvertently moved?

5. *Danny* - Any final measurements for fiber array bracket; when ready 
we'll ask for ~2 hr access to install

6. *Leke/Paul* - Ask Radcon to remove radioactive boundary rope; put 
roll around rack back where it came from

7. *PEPPo* - We should meet Wednesday 10:30am for regular meeting, for 
status updates & to list/prioritize access tasks.

8. *Riad/Erica* - Does PD have your request for next DAQ studies?

9. *John* - Once gun in routinely ~ON, I'll ask PD to coordinate a good 
time to test swapping HVPS


What else....?


-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/peppo/attachments/20111101/b08bc500/attachment.html 


More information about the PEPPo mailing list